Process for Engineering or Equipment change

linkedin twitter facebook  
avatar
Takesha McClane-Tsamis Project Manager| Illinois Tollway South Bend, In, United States
Can someone explain a process for Engineering changes or new equipment process? Need help coming up with a change management process. Project approval process seems to different than a change management approval process. To me it's the same.
Sort By:
avatar
Sromon Das Senior Project Manager| Mara Consulting Halifax, Nova Scotia, Canada
There are a number of change management models; Prosci is the most well known i believe- they an outline of their models on their website

/sd
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Takesha -

Are you referring to a production change control process or an organizational change management process as the two are quite different. The former might be performed within the lifecycle of a project to implement a production change to existing equipment whereas the latter will usually start before a project is initiated and will continue after the end of a project to ensure the sustainability of the implemented people/process/technology changes.

Kiron
...
1 reply by Takesha McClane-Tsamis
Jan 31, 2018 9:07 AM
Takesha McClane-Tsamis
...
A process and new equipment purchases
avatar
Takesha McClane-Tsamis Project Manager| Illinois Tollway South Bend, In, United States
Jan 31, 2018 9:05 AM
Replying to Kiron Bondale
...
Takesha -

Are you referring to a production change control process or an organizational change management process as the two are quite different. The former might be performed within the lifecycle of a project to implement a production change to existing equipment whereas the latter will usually start before a project is initiated and will continue after the end of a project to ensure the sustainability of the implemented people/process/technology changes.

Kiron
A process and new equipment purchases
...
1 reply by Kiron Bondale
Jan 31, 2018 11:02 AM
Kiron Bondale
...
You could review ITIL resources to get a good starting point for a production change control process, but as far as purchases goes, that should be defined via your organization's procurement standards or policies.

Kiron
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Jan 31, 2018 9:07 AM
Replying to Takesha McClane-Tsamis
...
A process and new equipment purchases
You could review ITIL resources to get a good starting point for a production change control process, but as far as purchases goes, that should be defined via your organization's procurement standards or policies.

Kiron

Please login or join to reply