Project Management

Please login or join to subscribe to this thread

what is correct answer

linkedin twitter facebook  
avatar
Asmaa Hamada Alexandria, Egypt
A project manager has to manage different stakeholder expectations. Project sponsor and customer are two very important stakeholders in any project. In this context, which of the following is NOT the responsibility of both the project sponsor and the customer?
1. Take into account risk tolerance
2. Provide key events, milestones, and deliverable due dates
3. Formally accept the product of the project
4. Provide financial resources for the project
Sort By:
< 1 2 >
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Asmaa -

I'd suggest the answer is 1. A sponsor and customer can definitely provide key milestones or due dates, they would be accepting the product of the project and one or both would provide funding.

Organizational and individual risk tolerance is something which the PM and team need to assess & take into account in a number of their activities & processes.

Kiron
...
1 reply by Nhlanhla Nxumalo
Feb 15, 2018 8:01 AM
Nhlanhla Nxumalo
...
Good day Mr Kiron I which to connect with you because I need a mentor It my first time to join MPI and I which to become a real project manager
avatar
Nhlanhla Nxumalo Functional Manager| HLTC group Johannesburg, Gauteng, South Africa
Feb 15, 2018 6:49 AM
Replying to Kiron Bondale
...
Asmaa -

I'd suggest the answer is 1. A sponsor and customer can definitely provide key milestones or due dates, they would be accepting the product of the project and one or both would provide funding.

Organizational and individual risk tolerance is something which the PM and team need to assess & take into account in a number of their activities & processes.

Kiron
Good day Mr Kiron I which to connect with you because I need a mentor It my first time to join MPI and I which to become a real project manager
avatar
Michael Coelho Neves Snr Project Manager| John Holland Brisbane, Australia
I would also suggest no 1. as its the PM and his team through the various tools and techniques that determine a sponsor and customers risk tolerance.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Fully agree with Kiron. I would chose 1 - Some people might chose 2 but since 1 is there, it is the most correct answer.
avatar
Anish Abraham Privacy Program Manager| University of Washington Auburn, Wa, United States
I agree with my colleagues here, and I would also go with the first choice.
avatar
Theresa Gilmore PMP Certified - Credit Risk Manager - Sr. Credit Analyst| Smurfit WestRock
I agree number 1 is the best choice of list given.
avatar
Stephen Karpowich Senior Product Manager Data and IP| CenturyLink Lenexa, Ks, United States
I don't like #1 due to the sponsor's need to understand the risks. While they may not know them up front, it seems that their awareness is a critical part of the project plan. If the risks are too great (financial, market competitive, resource assignments) wouldn't the sponsor have a say in either modifying or cancelling the project? With that in mind, I think the sponsor wouldn't have a lot of say with #2. They drive the project initiation, but those functions develop afterward though they would need awareness and concurrence after development.
avatar
Muthu Srinivasan Shanmugam PMP| CSM Chennai, India
Should be option 1
avatar
Kevin Drake Perth, Western Australia, Australia
If you eliminate the wrong answers, you end up with 1.
However, I agree with Stephen
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Colleagues, I would have to answer number 2.

Risk tolerance can be defined through EEF at the enterprise level, or at the ideation stage before a charter or even a PM is created. Risk tolerance is inherent at all levels of the organization and within every individual personality conveyed through conversation, during requirements analysis, stakeholder analysis, risk identification, assumption logging etc.

While the sponsor may "provide key events, milestones, and deliverable due dates", the customer generally doesn't. I know sometimes they are the same entity, but especially with eternal customers procuring project services, they generally don't.
...
1 reply by Kiron Bondale
Feb 15, 2018 5:25 PM
Kiron Bondale
...
Sante -

But is the sponsor and/or customer responsible for accounting for risk tolerance? As key decision makers, they might need to be aware of it, but wouldn't the PM and the team be the ones incorporating that knowledge into their planning efforts?

Kiron
< 1 2 >

Please login or join to reply

Content ID:
ADVERTISEMENTS

"You cannot prevent the birds of sorrow from flying over your head, but you can prevent them from building nests in your hair."

- Chinese Proverb

ADVERTISEMENT

Sponsors