When senior manager getting into your way in project management and they are influencing your project. Offcourse they do not have any bad intention but it is affecting your project. How to handle it.

linkedin twitter facebook   Agile   Communications Management   Requirements Management  
avatar
Manish Bhadauria Project Manager| Cignex Datamatics Pvt. Ltd New Delhi, Delhi, India
I have a very prestigious project and my senior manager is influencing a lot. He is connecting to resources directly bypassing me and sometimes coming up with urgent client pleasing requirements in between the Sprint. Please suggest how to handle it.
Sort By:
< 1 2 >
avatar
K . San Jose, Ca, United States
I am sure you are trying to ensure that all the changes and requests are getting logged with enough traceability on them in terms of why these were added, what was the impact to the schedule and risks and issues that have come up from any of these changes. It helps as part of learning lessons at the point of project closure or when next phase is being started. If not, you may want to do that. In a similar situation, those details went a long way for me in providing clear understanding to clients and internal stakeholders on what can be done better in future
avatar
Michael Delaney Partner| Delaney Management LLC West Chester, Pa, United States
Manish sounds like you handled this well, Toughest part about "prestige" projects is that they get a lot of attention from key stakeholders and that requires additional effort to manage them. Also you and your manager are both learning your roles in this situation so it good that you are communicating.