Project Management

Please login or join to subscribe to this thread

How does one best use the exam analysis provided by PMI

linkedin twitter facebook  
avatar
Geraldo Da Silva Brooklyn, Ny, United States
I need help in interpreting PMI analysis of my second PMP attempt. According to the analysis although I score higher in the tasks of Initiating and Planning it was deemed below target. It was explained to me the numbers of questions vary between tests, so that one can not really compare task scores between exam analysis documents.
Sort By:
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Geraldo -

That is correct - the percentages of questions are allocated to the process groups/domains and not to individual tasks so even if you were Below Target for a task, it doesn't mean that represented a large number of questions.

All you can do with this info is figure out what you might want to review in further detail prior to your next attempt.

Kiron
...
1 reply by Geraldo Da Silva
Mar 21, 2018 10:56 AM
Geraldo Da Silva
...
Thank you for your response.
avatar
Geraldo Da Silva Brooklyn, Ny, United States
Mar 21, 2018 10:53 AM
Replying to Kiron Bondale
...
Geraldo -

That is correct - the percentages of questions are allocated to the process groups/domains and not to individual tasks so even if you were Below Target for a task, it doesn't mean that represented a large number of questions.

All you can do with this info is figure out what you might want to review in further detail prior to your next attempt.

Kiron
Thank you for your response.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
I agree with Kiron, as far as I am aware, the questions are drawn from a large pool of questions randomly so even if two candidates were besides each other, their questions are different. That is what I know.
avatar
Narasimha Rao A V L Project Manager| DST IT Services Hyderabad, Telangana, India
One thing that you may have to consider as far as the analysis is considered -

While you may not get the same number of questions for a given task across multiple exams, the fact remains that if you did not score high in a particular task, you should focus on that area, though the overall score on the Process Group looks better.
...
1 reply by Geraldo Da Silva
Mar 21, 2018 1:47 PM
Geraldo Da Silva
...
Understood. Thank you.
avatar
Geraldo Da Silva Brooklyn, Ny, United States
Mar 21, 2018 1:44 PM
Replying to Narasimha Rao A V L
...
One thing that you may have to consider as far as the analysis is considered -

While you may not get the same number of questions for a given task across multiple exams, the fact remains that if you did not score high in a particular task, you should focus on that area, though the overall score on the Process Group looks better.
Understood. Thank you.
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
The exam breakdown PMI gives you is a great tool to pass on your next attempt.
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
The tool to evaluate percentages is the Context Outline using the Domain section. But believe me, it has no sense to evaluate it. Including it has no sense to be happy or unhappy if you get the certification above or below the target. That said nothing about you as project manager. As the PMI stated a certification only demonstrate that you have enough knowledge about the application to all PMI stated into a project. But as you know, when you go to the real world, some of things that will help you to answer a question do not fit for being applied into your daily reality. And that´s not mean that you are not able to get the project success.
...
1 reply by Geraldo Da Silva
Apr 05, 2018 8:42 AM
Geraldo Da Silva
...
Thank you for your thoughtful reply.
avatar
Geraldo Da Silva Brooklyn, Ny, United States
Mar 31, 2018 12:14 PM
Replying to Sergio Luis Conte
...
The tool to evaluate percentages is the Context Outline using the Domain section. But believe me, it has no sense to evaluate it. Including it has no sense to be happy or unhappy if you get the certification above or below the target. That said nothing about you as project manager. As the PMI stated a certification only demonstrate that you have enough knowledge about the application to all PMI stated into a project. But as you know, when you go to the real world, some of things that will help you to answer a question do not fit for being applied into your daily reality. And that´s not mean that you are not able to get the project success.
Thank you for your thoughtful reply.
avatar
Teresa Lawrence, PhD, PMP, CSM President| International Deliverables, LLC Hilton Head Island, SC, United States
In addition to what others have said - it is an area on which you need to focus to be successful on your third attempt, I would ADD...keep these areas in mind when you are securing your 60 PDUs once you become a PMP.
Teresa

Please login or join to reply

Content ID:
ADVERTISEMENTS

"Time is an illusion, lunchtime doubly so."

- Douglas Adams

ADVERTISEMENT

Sponsors