Question on Risk Burndown Chart

linkedin twitter facebook   Agile   Risk Management  
avatar
Anonymous
In Agile risk management, a risk burndown chart is best used to:

a. qualitatively analyze the probability of a risk occurring.

b. illustrate the project risk profile and new and changing risks.

c. track progress on risk reduction of technical risks.

d. document the external risks that could impact the project.
Sort By:
< 1 2 >
I am going with C. track progress on risk reduction of technical risks.