In the Close Project or Phase process, historical information is considered a(n) ____________.
a. input
b. output
c. input as well as an output .
d. None of the above Saving Changes...
Sort By:
Anonymous
This question is answered: C is correct.
Missed additional information which rolled over to next page of the PMBOK guide.
At first was wondering if the current project can consider its own info historical, or if only future projects will consider info from the current project as historical. This is clarified in guide. Saving Changes...