Question on Direct and Manage Project Work

linkedin twitter facebook  
avatar
Anonymous
Project documents that may be required in order to direct and manage project work include:_____________

a. Lessons learned register, Risk report, Requirements traceability matrix

b. Corrective actions; Preventive actions; Defect repairs

c. Organizational standard policies, processes, and procedures; Defect management procedures; Risk control procedures

d. Assumption log; Risk register; Stakeholder register
Sort By:
avatar
Mahabubur Rahman Project Manager Structures-Bridges| Department of Infrastructure, Government of Nothwest Territories Yellowknife, Northwest Territories, Canada
"b" seems to be more relevant.
avatar
Anonymous
Are option b items project documents?
avatar
Mahabubur Rahman Project Manager Structures-Bridges| Department of Infrastructure, Government of Nothwest Territories Yellowknife, Northwest Territories, Canada
Yes, these are under "Approved change requests"-which is an input to the "Direct and Manage Project Work" process.
avatar
Anonymous
I see about Approved Change Requests.

Option C has a control item, so seems incorrect. How are A and D eliminated? Is 'Lessons learned register' non-existent...?

This site stated option A as the correct answer (site is often wrong though).