Issues, Issues... setting up permissions for submission of new issues

linkedin twitter facebook   New Practitioners  
avatar
Matthew D. Martin Chief of Product| Meribah Flow Consultants, Inc. Vancouver, BC, Canada
Question for you practitioners out there: what degree of transparency and edit-ability do you set up for your Issue Log, in relation to you project team?

For example, one configuration is that everyone can read, but it’s read only (say, in Excel) and potential new issues are sent to PM for review. Or, anyone can generate and list an issue that’s come up for them (no prior vetting if issue). Or you as PM own the list and only make it visible at team meetings, and are the only one to officially creat new issues on the list?

Would appreciate any tips on managing this process.
Sort By:
< 1 2 >
avatar
Tiago Romao Project Manager - PfMP | PgMP | PMP | ACP | PBA | CBAP | CSM | MSc.| Altice Portugal | Meo Sobreda, Setubal/Almada, Portugal
I'm using PMI template, i.e. the excel file has an issue log and an action log. I do weekly reviews of the action log. On the issues log, i track issues :) i followup them through email, phone or even 30 min meetings. I also use Jira in one of the projects.