What is the best way to manage 91 projects with the same timeline (wbs) when using project management software? The wbs will have at least 60 tasks that need to be done however if you multiply that by 91 that's alt lol. Saving Changes...
Sergio Luis ConteHelping to create solutions for everyone| Worldwide based OrganizationsBuenos Aires, Argentina
Please let me say there are some mistakes (as far I understood) into your statement. 1-WBS has not timeline into it. So, sombody is mixing things. 2-Just in case you have an schedule wich contains 91 subschedules you are in trouble. What you have is a program and the best way is to create an schedule for a program, link the schedules for each project to the schedule to the program, and maintained it in separate way. What you stated is about quality. Deliverables has quality attributes that you have to take into account. Each document you create must achieved these quality attributes:
a) Correct;
b) Unambiguous;
c) Complete;
d) Consistent;
f) Verificable;
g) Modificable;
h) Traceable. Saving Changes...