Harish Pawar Project Consultant| Saudi Electricity Company- Dar Engineering Riyadh, Central, Saudi Arabia
You are the project manager in an aircraft manufacturing company developing a new range of supersonic fighter planes. Since government approval and involvement are essential, you hire a lobbying firm to get government support to prevent unnecessary changes in your project. Which process is this an example of?

1. Perform Integrated Change Control

2. Risk Management

3. Cost Management Plan

4. Develop Project Management Plan
Sort By:
< 1 2 3 >
avatar
Moloy Chakraborty Principal Project Manager| WSP UK LTD High Wycombe, Buckinghamshire, United Kingdom
Apr 21, 2018 8:55 AM
Replying to Clark Edwards
...
Good question. Answers 2 and 3 are not Processes. Start at beginning and work down. We have an EEF - EXTERNAL would be considered a constraint in Charter. We hire during Initiating - lobbying firm - and we have a new stakeholder who we hope will keep our SCOPE INTACT throughout the Project. BEST ANSWER would be 1 Perform Integrated Change Control (Inputs include EEF's and Change Requests which we don't want if they result in SCOPE change). Answer 4 focuses on how we are going to manage all of our "plans" - not applicable in this instance.
Agree with your answer i.e. option-1, Perform Integrated Change Control
avatar
MUHAMMAD NASIM UDDIN Technical Consultant| MilRine Pro Houston, Tx, United States
As seemed, the project is probably in the early stages of developing Project Management Plan and in that cost and risk management parts are under deliberations. Since the government approval/ involvement is mandatory to be considered (as risk) for the project, therefore, hiring a lobbying firm is a logical move to get government support for the project so that future changes can be prevented in your project in the documented manner. The outcome of this effort will certainly help PM in efficiently incorporating both the Cost as well as Risk plans while developing Project Management Plan. My answer is 4 (despite it is not a process but it initiates a lot number of processes in the projects)
< 1 2 3 >

Please login or join to reply

Content ID:
ADVERTISEMENTS

Waiting for the time when I can finally say that this has all been wonderful but now I'm on my way.

- Phish

ADVERTISEMENT

Sponsors