Can anybody share a risk register template for Pipeline Project ?

linkedin twitter facebook   Risk Management  
avatar
Kathy Castle Author at https://www.projectcubicle.com/| Freelance Tx, United States
Can anybody share a risk register template for Pipeline Project ?
Sort By:
avatar
Aaron Porter
Community Champion
IT Director| Blade HQ Payson, UT, United States
Oil pipeline?

Are you looking for predefined risks?
avatar
Kathy Castle Author at https://www.projectcubicle.com/| Freelance Tx, United States
For predefined risks in Oil pipeline projects
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
I would access some journal articles. For example, when i googled "projects risks for oil pipeline projects" you will see a bunch of PDF articles on risk in oil projects such as:

https://www.kent.ac.uk/scarr/events/Mubin.pdf
...
1 reply by Kathy Castle
Apr 26, 2018 1:24 AM
Kathy Castle
...
Thank you Sante
avatar
JOONMIN SUH Project Engineering Manager| Samsung Construction & Trading Seongnam, Gyeonggi, South Korea
Hi, Kathy
I believe RBS(Risk Breakdown Structure) will be more helpful considering following categories;
Environmental, Geotech, Design, ROW(Right of way), Utilities, Crossing(Rail, Bridge, etc.), Partnership and Stakeholders, Management or Funding, Contracting / Procurement and Construction.
avatar
Kathy Castle Author at https://www.projectcubicle.com/| Freelance Tx, United States
Apr 23, 2018 5:30 PM
Replying to Sante Delle-Vergini, PhD
...
I would access some journal articles. For example, when i googled "projects risks for oil pipeline projects" you will see a bunch of PDF articles on risk in oil projects such as:

https://www.kent.ac.uk/scarr/events/Mubin.pdf
Thank you Sante
...
1 reply by Sante Delle-Vergini, PhD
Apr 26, 2018 2:32 AM
Sante Delle-Vergini, PhD
...
You're welcome :-)
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Apr 26, 2018 1:24 AM
Replying to Kathy Castle
...
Thank you Sante
You're welcome :-)