1%-10% Rule
last edited by: Ethan Dwyer on Nov 6, 2020 3:05 PM | login/register to edit this page |
![]() The 1%-10% Rule is used to determine the proper level of detail while breaking down the work of a project. The rule states that the lowest level of activities in the WBS of a project should have a duration no less than 1% of the project duration and not more than 10% of the project duration. For example, if your project will be about 1 year (about 240 business days) long, you have the responsibility to break your project down into as many levels of detail such that activities are:
10 years = about 5 weeks. Subsequently the program manager identifies the subprojects and assigns the subproject managers. Each subproject manager continues the breakdown of the program but only within their own subproject applying the 1%-10% Rule again but only to their subproject. If one subproject manager thinks his/her subproject will take about 1 year, the minimum duration for their activities is 2 business days and the maximum duration is 5 weeks. The 1%-10% Rule was first published by Eric Uyttewaal in his book "Dynamic Scheduling with Microsoft Project 2000" in the year 2000.
|
|
last edited by: Ethan Dwyer on Nov 6, 2020 3:05 PM | login/register to edit this page |
Comments (3)
Don't ever take a fence down until you know why it was put up. - Robert Frost |