What are the major project closure activities, when an project is suspended or terminated by the customer.
Are all the project closure activities and documentation to be followed in this case as done in normal project closure , after successful completion of project.
Looking forward in receiving the answers. Saving Changes...
Wade HarshmanScrum Master| GDITIndianapolis, In, United States
Don't forget to change your email and phone number after closing a project, so the sponsor can't call you a year later with questions and scope creep.
Just kidding.
...mostly. Saving Changes...
VASUDEV NARAYANANProgram Manager| Pentapolis FoundationChennai, Tamil Nadu, India
First, look at your Contract and understand the steps mentioned under the the exit criteria You will need to follow the steps that are mentioned in the Contract. If the Contract does not have an Exit Clause,
During suspension or termination of projects, you may need assistance from the Legal and Financial professionals along with the sponsor(s) to understand the implication. Apart, as per the normal closure, you will need to conduct the closure activities. Saving Changes...