Project closure action

linkedin twitter facebook   Estimating   Lessons Learned  
avatar
Dattprasad Bhaskar Vernekar Senior Manager Bengaluru, Karnataka, India
What are the major project closure activities, when an project is suspended or terminated by the customer.
Are all the project closure activities and documentation to be followed in this case as done in normal project closure , after successful completion of project.
Looking forward in receiving the answers.
Sort By:
< 1 2 >
avatar
Wade Harshman Scrum Master| GDIT Indianapolis, In, United States
Don't forget to change your email and phone number after closing a project, so the sponsor can't call you a year later with questions and scope creep.

Just kidding.

...mostly.
avatar
VASUDEV NARAYANAN Program Manager| Pentapolis Foundation Chennai, Tamil Nadu, India
First, look at your Contract and understand the steps mentioned under the the exit criteria You will need to follow the steps that are mentioned in the Contract. If the Contract does not have an Exit Clause,
During suspension or termination of projects, you may need assistance from the Legal and Financial professionals along with the sponsor(s) to understand the implication. Apart, as per the normal closure, you will need to conduct the closure activities.
avatar
Ali Hossam Sr.Planning Engineer| CCC Qatar

Agree 


avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Yes, you have to perform project closure activities. Everybody must agree about the final status of the project.