Why 'Rolling Wave Planning' not impacting Estimate Cost & Determine Budget process?

linkedin twitter facebook   Agile   Benefits Realization   Change Management   Cost Management   Earned Value Management   Estimating   Schedule Management   Scheduling   Using PMI Standards   Work Breakdown Structures (WBS)  
avatar
Mukunda Adhikari, PMP® C&PM| Nokia Noida, Uttar Pradesh, India
Hi PMs,
Just a query on rolling wave planning.
During course of execution, we come to planning to define activities and create CR and may update schedule baseline with approved CR but why not in cost? Why rolling wave planning not impacting Estimate Cost & Determine Budget process?
Ideally as a part of rolling wave planning, it should impact the cost in planning.

Any idea?

Welcomed any views for further discussion.

Thanks.
Sort By:
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Perhaps I do not understand your point but there are situations where the schedule has to be change without impacting the cost. On the other side, plan is not only schedule is all related to a plan then rolling wave planning could impact all related to plan indeed (scope, cost, risk, stakehodlers, etc. etc)
...
1 reply by Mukunda Adhikari, PMP®
Oct 01, 2018 2:27 PM
Mukunda Adhikari, PMP®
...
Hi Sergio,
The rolling wave planning is tool for define activities process but not for estimate cost and determine budget. If activities are getting updated, the estimate cost should also be impacted due to rolling wave as new activities may need additional cost estimates.
And which may cause change in cost baseline as well with approved CR.
avatar
Mukunda Adhikari, PMP® C&PM| Nokia Noida, Uttar Pradesh, India
Oct 01, 2018 2:22 PM
Replying to Sergio Luis Conte
...
Perhaps I do not understand your point but there are situations where the schedule has to be change without impacting the cost. On the other side, plan is not only schedule is all related to a plan then rolling wave planning could impact all related to plan indeed (scope, cost, risk, stakehodlers, etc. etc)
Hi Sergio,
The rolling wave planning is tool for define activities process but not for estimate cost and determine budget. If activities are getting updated, the estimate cost should also be impacted due to rolling wave as new activities may need additional cost estimates.
And which may cause change in cost baseline as well with approved CR.
...
1 reply by Sergio Luis Conte
Oct 01, 2018 3:31 PM
Sergio Luis Conte
...
Sorry but let me say you are wrong. As its name stated is about planning and planning is to create a plan and a plan is a document with contains all related to knowledge areas you have to include: scope, risk, stakeholders, etc, etc.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Besides Rolling Wave Planning is used for cost estimates - I am not sure how you concluded that it is not.

During progressive ellaboration when you add more detail to the WBS as enough info is revealed, your estimates will become more precise because instead of estimating a full planning package, you estimate decomposed planning package.
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Oct 01, 2018 2:27 PM
Replying to Mukunda Adhikari, PMP®
...
Hi Sergio,
The rolling wave planning is tool for define activities process but not for estimate cost and determine budget. If activities are getting updated, the estimate cost should also be impacted due to rolling wave as new activities may need additional cost estimates.
And which may cause change in cost baseline as well with approved CR.
Sorry but let me say you are wrong. As its name stated is about planning and planning is to create a plan and a plan is a document with contains all related to knowledge areas you have to include: scope, risk, stakeholders, etc, etc.
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Mukunda -

Just because rolling wave planning shows up as a tool in Define Activities but doesn't in Estimate Costs doesn't mean one doesn't impact the other.

The PMBOK Guide doesn't show ALL the relationships from one process to another, and remember that the schedule IS an input into Determine Budget so after elaborating further activities when we update our schedule we might have to iterate back to Determine Budget to understand if costs have changed...

Kiron
...
1 reply by Mukunda Adhikari, PMP®
Oct 01, 2018 8:52 PM
Mukunda Adhikari, PMP®
...
Thanks Kiron. Your answer is somehow justifying.
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
After reading Kiron´s post now I understood the point. Inside the PMBOK you will find references to rolling-wave-planning in several pages. For example, references when things related to WBS are stated, when some things related to schedule, etc. So, while it is named as a tool in Define Activities you will find rolling-wave-planning references in several other places as a way to create a plan.
...
1 reply by Mukunda Adhikari, PMP®
Oct 01, 2018 8:54 PM
Mukunda Adhikari, PMP®
...
Yes Sergio, you are right but couldn't find in PMBOK Guide.
avatar
Mukunda Adhikari, PMP® C&PM| Nokia Noida, Uttar Pradesh, India
Oct 01, 2018 5:35 PM
Replying to Kiron Bondale
...
Mukunda -

Just because rolling wave planning shows up as a tool in Define Activities but doesn't in Estimate Costs doesn't mean one doesn't impact the other.

The PMBOK Guide doesn't show ALL the relationships from one process to another, and remember that the schedule IS an input into Determine Budget so after elaborating further activities when we update our schedule we might have to iterate back to Determine Budget to understand if costs have changed...

Kiron
Thanks Kiron. Your answer is somehow justifying.
avatar
Mukunda Adhikari, PMP® C&PM| Nokia Noida, Uttar Pradesh, India
Oct 01, 2018 5:48 PM
Replying to Sergio Luis Conte
...
After reading Kiron´s post now I understood the point. Inside the PMBOK you will find references to rolling-wave-planning in several pages. For example, references when things related to WBS are stated, when some things related to schedule, etc. So, while it is named as a tool in Define Activities you will find rolling-wave-planning references in several other places as a way to create a plan.
Yes Sergio, you are right but couldn't find in PMBOK Guide.