Shorten target date with same resources and quality.

linkedin twitter facebook   Quality   Resource Management   Schedule Management   Scheduling  
avatar
Talat Alpan Aytekin Solution Development Specialist| Turk Telekom Sisli, Istanbul, Türkiye
Today in a job interview, I was asked what would I do if the project target date needed to be shortened with the same resources. I suggested to decrease the quality but that was rejected. Does anyone have a proper answer?
Sort By:
< 1 2 3 >
avatar
Steve Ratkaj Ontario, Canada
The answer to these types of "situational" questions are not simple "one liners". The interviewers are looking to see how you would "deal" with the situation from a managerial perspective. We have similar situational type questions when vetting candidates for higher-level positions. Failure rates are typically 40% - 60% and those that passed have done their homework. I think Vasudev had some good points to consider.
avatar
Al Taylor I.T. Contractor| Independent Waterloo, Ontario, Canada
A punch in the face for the interviewer?
avatar
Suzi MS United Kingdom
I only realised now that topic was raised over a year ago Talat, hope you’ve since moved on and secured a role. Please do keep the community updated! :-)