Thanks for the detailed and quick reply. I do find the ITTOs to be a great summary of different knowledge areas and processes in project management. But some of the inputs and outputs are not easy to grasp and are counter-intuitive.
e.g. Work Performance Reports and Work Performance Data are input in Monitor Risks process. But Work Performance Information is output for the same process.
In Control Procurement process, Approved Change Request is input but output is Change Request. This can be explained only with understanding of insight into built-in context.
Also Presentations are part of tools for Monitor Stakeholder engagement but not part of Manage Stakeholder Engagement. That is difficult to imagine for anybody part of regular stakeholder meetings and interactions.
Sometimes the tacit knowledge in ITTOs is complemented with explanations in the guide but other times it has been left unexplained.