Anyone know where BCWS comes from in MS Project 2000?

linkedin twitter facebook  
avatar
Chuck Egerter Tampa, Fl, United States
Hi,

I was thinking that BCWS would come from scheduled hours times resource rates. However, I have saved the project baseline, I have resources (with rates) assigned to my tasks, I have an overall cost and schedule, but when I look at the earned value view, BCWS, BCWP are showing up as zero. I do get values for ACWP - but my CVs are off. Any ideas what is happening here? Thanks for any help.
avatar
Hafeez Rahman Teacher| Bahria University Karachi, Pakistan
I have been facing similar problem. I am using MS Project 98.

First make sure that the task is not 100% complete say it is only 50%. Than go to TABLE, MORE TABLES, EARNED VALUE. You would able to see something like this:
BCWS 10,000
BCWP 5000
ACWP 6000
CV 1000
SC 5000

You may contact me directly at
[email protected]