I was thinking that BCWS would come from scheduled hours times resource rates. However, I have saved the project baseline, I have resources (with rates) assigned to my tasks, I have an overall cost and schedule, but when I look at the earned value view, BCWS, BCWP are showing up as zero. I do get values for ACWP - but my CVs are off. Any ideas what is happening here? Thanks for any help. Saving Changes...
I have been facing similar problem. I am using MS Project 98.
First make sure that the task is not 100% complete say it is only 50%. Than go to TABLE, MORE TABLES, EARNED VALUE. You would able to see something like this: BCWS 10,000 BCWP 5000 ACWP 6000 CV 1000 SC 5000