Project Management

Please login or join to subscribe to this thread

an issue that occurred several weeks ago

linkedin twitter facebook   Risk Management   Strategy   Using PMI Standards  
avatar
AMANY emam Cairo, Egypt
A project manager realizes that an issue that occurred several weeks ago has negatively impacted the schedule. when the mitigation plan is initiated, it fails because the required resources are now unavailable. what should the project manager done to avoid this?
A. conducted stand-up meetings to communicate project status
B. Sent out status reports to stakeholders
C. reviewed and updated the risk mitigation plan
D. updated the resource management pan.
Sort By:
avatar
Kwiyuh Michael Wepngong
Community Champion
Financial Management Specialist | US Peace Corps Yaounde, Centre, Cameroon
Hi Amany,
what should the project manager done to avoid this or these...
There is a schedule issue here and a resource deficiency
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Amany -

This is a poorly written question. A mitigation plan is something you would implement to reduce the probability and/or impact of a negative risk being realized. In this case, the risk has been realized, so it would no longer be a mitigation plan but rather a contingency plan.

Out of the choices provided, the most likely answer is "C", but again, I would have reworded that to be risk response plan to be a little more general.

Kiron
avatar
Keith Novak Tukwila, Wa, United States
The answer is C. The mitigation plan was already out of date when the risk was realized.

To avoid the risk of having an out of date mitigation plan, the plan should be regularly be reviewed and updated.
avatar
Peter Rapin Subject Matter Expect; Project Delivery| Independent Consultant Ontario, Canada
The Risk Management Plan failed on a coupe of levels here. Apparently the Plan identified the risk event and provided for mitigation should it occur. However the Plan did not have a process to recognize the risk event when (if) it occurred and the mitigating measure did not address the resource requirements. What makes you think the the resources would have been available several weeks earlier had the need been recognized? If the risk event was to occur several weeks later (the present) what makes you think the resources would be available?

The Plan needs to be updated to:
1) establish a process to recognize risk event when they occur
2) make sure the mitigating measures are available when the risk event is identified as occurring, and
3) update the occurring risk as an issue and record the response (or lack thereof) with resulting project impact.

Question: does the Plan say "place on shelf and ignore" or is there a review and update requirement built-in?
avatar
Asif Gul Consultant Project Manager| Energoprojekt Entel Muscat, Oman
C- Because,
most of the time while recording any issue , we do analysis on its impact and the risk(s) being perceived due to that particular issue.

Please login or join to reply

Content ID:
ADVERTISEMENTS

"The brain is a wonderful organ. It starts the moment you get up and doesn't stop until you get into the office."

- Robert Frost

ADVERTISEMENT

Sponsors