Managing project status is as different as you have stakeholders attached to your project. You will have to provide the project status with the content and the format relevant to each stakeholder.
What you have to do to is to work on your project status data to allow you to present information in different ways. That means your activities' duration should be no larger than the most frequent project status cycle.duration. In other words, if you have to report on a daily basis, make sure your activities are less than a day in duration. You can then roll-up to a weekly, monthly, or quarterly status updates as necessary. Saving Changes...