Adheesh, this is a very straight forward question. The Agile team estimated velocity is 8 Points per Sprint so the sum of points for all stories included in the sprint shouldn't exceed 8 points:
Option 1 - Total = 9 Points so its not the right choice.
Option 2 - Total = 9 Points so its not the right choice.
Option 3 - Total = 8 Points so its the correct answer
Option 4 - Total = 7 Points and while it can be a correct answer yet, option 3 is more correct because their velocity is 8 stories so why would they consider less than that if they accomodate 8.
Hope this helps explain!