FIRST QUESTION IN OUR QUESTION SERIES :
QUESTION ( 1):
A project team has completed all the technical project deliverables, and the customer has accepted the deliverables. However, the lessons learned required by the project office have not been completed. What is the status of the project?
A.The project is incomplete because the project needs to be re-planned
B.The project is incomplete until lessons learned are completed.
C.The project is complete because the customer has accepted the deliverables
D.The project is complete because the project has reached the due date
?#?proactive? . Saving Changes...
Sort By:
HEMAM RANJIT KUMAR SINGHFounder & Director| TechSure Global Consultancy LLPGuwahati, Assam, India
I would like to choose Option # B.The project is incomplete until lessons learned are completed. Saving Changes...
yes , but why ? all deliverables are being carried out only lesson learned . Saving Changes...
HEMAM RANJIT KUMAR SINGHFounder & Director| TechSure Global Consultancy LLPGuwahati, Assam, India
hi Shaban,
As per PMBOK Guide Fifth Edition , Reference Page # 58 , 4th Bullet Point , it is clearly mentioned to document Lesson Learned in the Closing Process Group.
Moreover , while preparing for my PMP certification , this very question was discussed in many PMP Forums , where the SMEs are in the opinion of choosing this LL option.
"We should be careful to get out of an experience only the wisdom that is in it - and stop there; lest we be like the cat that sits down on a hot stove-lid. She will never sit down on a hot stove-lid again, and that is well; but also she will never sit down on a cold one anymore."