Hi Experts ,
Lets say , a project has CPI = .9 and SPI = .9 .
So, CPI < 1 ie. the project is Over Budget and SPI < 1 ie. the project is Behind Schedule .
CPI = .9 ie. ( 1 - .9 ) = .1 ie. ( 1 / 10 ) x 100 = 10 % . So, the project is 10% Over Budget.
SPI = .9 ie. ( 1 - .9 ) = .1 ie. ( 1 / 10 ) x 100 = 10 % . So, the project is 10% Behind Schedule.
I am unable to understand , why are we doing ( 1 - .9 ) ie. why I am deducting .9 from 1 ?
CPI = .9 , so , I could have said that , project is Over Budget by .9 ie. ( 9 / 10 ) x 100 = 90 %
SPI = .9 , so , I could have said that , project is Behind Schedule by .9 ie. ( 9 / 10 ) x 100 = 90 %
Why I am deducting .9 from 1 ?
Sorry , if this sounds a silly question !
Thanks & Regards
Saswata Mandal