How do you decide whether a late access constraint needs escalation?

linkedin twitter facebook  
avatar
Mohamed Maged Hegazy Head of Contract & Project Control| Shaker Consulting Group Riyadh, Saudi Arabia

An installation crew loses access to its work area. The handover forecast holds because the team expects to resequence the work. At the next progress meeting, how would you test that recovery assumption, and what would make you escalate it?

يتعذّر على فريق التركيب الوصول إلى منطقة العمل. ويظل موعد التسليم المتوقع قائماً لأن الفريق يتوقع إعادة ترتيب الأعمال. كيف ستختبرون افتراض التعافي في اجتماع المتابعة المقبل؟ ومتى ستصعّدون الأمر؟

Sort By:
avatar
Neethu Chandra Babu Doha, Qatar
I escalate a late access constraint as soon as the delay starts impacting the critical path or putting key milestones at risk. If there’s no practical workaround to keep the team productive and normal follow-ups haven't cleared the bottleneck, it’s time to bring leadership in to help unblock it. When I do escalate, I make sure to clearly outline the timeline impact and suggest a quick resolution or temporary workaround
avatar
Michael King
Community Champion
Senior IS Project Manager| Baycare Health Systems Clearwater, Fl, United States
Mohamed - I would escalate this immediately. This has a critical impart to your project schedule and deliverables. I find as a project manager one of my main responsibilities is to help the team complete their assignments and this is one escalation that can help them get back on track.