How do you trace a schedule slip back to where it actually started?

linkedin twitter facebook   Schedule Management  
avatar
Sandeep Kashyap CEO| ProofHub India

When a project falls behind, the review naturally starts with the activity that missed its deadline. That's where the delay becomes visible, so that's where the questions begin.

But the late activity isn't necessarily where the delay started. A dependency might have remained unresolved for days or even weeks while the activity continued to show as "in progress."

Unless the team tracks these waiting periods separately, they can go unnoticed in the schedule. By the time someone investigates, they have to piece together what happened from emails, meeting notes, and people's recollections.

The review then risks focusing on the activity that finished late and the person responsible, rather than the unresolved dependency that held it up.

I'm curious how other teams handle this in practice: Do you track waiting time and decision turnaround separately from task progress? How do you keep post-delay reviews focused on understanding upstream causes rather than finding someone to blame?

I'd particularly like to hear from people who changed how they track waiting time because of this.