How do you validate resource assumptions in a construction baseline?

linkedin twitter facebook   Construction  
avatar
Mohamed Maged Hegazy Head of Contract & Project Control| Shaker Consulting Group Riyadh, Saudi Arabia

A baseline can pass a logic review while several packages still depend on the same crew, crane or work area. One check is to compare a key activity duration with the quantity, actual output per shift, work calendar and site access. Reviewing that calculation with the delivery team can surface the most consequential assumptions before sign-off.

Which evidence do you require to validate a critical resource assumption before approving the baseline?