Aug 28, 2017 12:56 PM
Replying to Hatem Haffar
...
It is very easy question and you need to use logic to answer that.
The answer is not A as Sean said.
I will explain it to you, so next time you will know how to answer.
The question tell you that you received a change request.
therefore it is not logical to create another change request since you already have one. so A is not correct.
(Evaluate the impact of the change): we always have to evaluate the cost and schedule impact and assess if any new risk will appear and redo the plan. It is logic answer, I will keep my eye on it and look for other answers.
(Communicate the implication of the change to the customer): How can I communicate the implication of the change while I didn't evaluate the impact yet. So C is incorrect.
(Adjust the project Management plan and baseline): what changes have to be done in the plan? do I need more resources? more time? more cost? I need to evaluate and study before changing the plan. so D is incorrect.
at the end you are only left with one logical answer B.