Schedule Compression - Crashing

linkedin twitter facebook   Risk Management   Scheduling   Using PMI Standards  
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Do you consider paying a vendor more to deliver a critical path activity sooner as a schedule crashing technique ?
Sort By:
< 1 2 >
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Jan 23, 2016 10:54 PM
Replying to Suhail Iqbal
...
It is all in the contract, if we compress the schedule by crashing the terms of contract can be re-negotiated, and we may pay him more but under new conditions to complete on new earlier date.
I agree with that but paying the SC to do the same work with less time is incentive so why do we need to change the contract terms and renegotiate ?
avatar
PANKAJ KUMAR JOSHI General Manager| Transrail Lighting Limited Nainital, Uttrakhand, India
Every vendor and subcontractor has the PO for doing works. He submits us the timeschedule in accordance with project schedule.

If we have to change the conditions of PO, we have to renegotiate. However sometime we cannot renegotiate it because of organisations contracting systems.

That time we managed it with sub contractor by personal influences or by speeding up the invoice approval time (no extra cost). I would say if we have to speed up we have to find the ways.
avatar
Anonymous
I would give it a green signal when consequences can be better.