George LewisProgram/Project Manager| DXC Technology CompanyHeredia, Costa Rica
Anybody else found errors?
I'm creating a log with the wrong answers and correcting only those that I think are wrong... It might be of help to someone.
...
1 reply by Karthik T
Jul 18, 2016 2:30 PM
Karthik T
...
Well done George! Really appreciate your effort!
Saving Changes...
George LewisProgram/Project Manager| DXC Technology CompanyHeredia, Costa Rica
Any more comments here? Saving Changes...
Deborah WaitzmanHealthcare Engineer / Architect / PM| Department of Veteran's AffairsWashington, DC, United States
Feb 10, 2016 6:41 AM
Replying to George Lewis
...
Error found, not of PMBOK 5th edition
_____ is the process of making relevant information available to project stakeholders as planned.
Identify Stakeholders
Distribute Information
Distribute Information is the process of making relevant information available to project stakeholders as planned.
Report Performance
Plan Communications
So true. Glad to find this post. Saving Changes...
Some questions are out dated but many are still valid. I strongly recommend PMP aspirants experience these questions before taking the PMP exam since it might be helpful to understand key concepts of ITTOs in PMBOK. It might be necessary to update before PMP exam is based on PMBOK 6th edition. Saving Changes...
Karthik TSenior Engineering Manager| NikeBangalore, Karnataka, India
Mar 02, 2016 5:13 AM
Replying to George Lewis
...
Anybody else found errors?
I'm creating a log with the wrong answers and correcting only those that I think are wrong... It might be of help to someone.
Well done George! Really appreciate your effort! Saving Changes...
Stéphane ParentSelf Employed / Semi-retired| Leader MakerPrince Edward Island, Canada
Markus is worried that the PMChallenge questions are not in PMP-exam format. That is true. As I have found in preparing for my SP and, now, RMP exams, most mock exams do not follow the PMI-style of questions. I expect that is on purpose to avoid any intellectual property disputes. Saving Changes...
Stéphane ParentSelf Employed / Semi-retired| Leader MakerPrince Edward Island, Canada
I'm trying to get my last Ace badge. In the process, I stumbled across this question.
Q. Which of the following is not an example of a project schedule output in the Develop Schedule: Outputs process?
bar charts
milestone charts
project schedule network diagram
All of the above
PMchallenge wants you to pick All of the above, then gives you the following description.
Each of the options presented is an example of a project schedule output in the Develop Schedule: Outputs process.
The correct answer should be None of the Above.
...
1 reply by Rami Kaibni
Oct 25, 2016 12:42 PM
Rami Kaibni
...
Stephane,
As far as I am concerned "All of the Above" is the correct answers as none of those are Outputs of Develop Project Schedule, they are Inputs so the question is correct but the reasoning might be wrong, they should have mentioned Input. The outputs of develop schedule are:
Senior Projects Manager | Field & Marten AssociatesNew Westminster, British Columbia, Canada
Oct 25, 2016 11:56 AM
Replying to Stéphane Parent
...
I'm trying to get my last Ace badge. In the process, I stumbled across this question.
Q. Which of the following is not an example of a project schedule output in the Develop Schedule: Outputs process?
bar charts
milestone charts
project schedule network diagram
All of the above
PMchallenge wants you to pick All of the above, then gives you the following description.
Each of the options presented is an example of a project schedule output in the Develop Schedule: Outputs process.
The correct answer should be None of the Above.
Stephane,
As far as I am concerned "All of the Above" is the correct answers as none of those are Outputs of Develop Project Schedule, they are Inputs so the question is correct but the reasoning might be wrong, they should have mentioned Input. The outputs of develop schedule are: