Project Management

Please login or join to subscribe to this thread

Difference between baseline date & forecast date

linkedin twitter facebook   Benefits Realization   Estimating   Information Technology   PMO  
avatar
Robin Gumber New Delhi, India, India
Difference between baseline date & forecast date
Sort By:
avatar
Justin Wortley Project Manager| Quicken Loans Detroit, Mi, United States
A baseline date is a target date, and a forecast date is a best guess. Baseline is the date at which the progress is being measured, but the forecast is the best guess to what will happen in the future.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
As Justin mentioned, a baseline date is a milestone or target date but forcast date is based on estimates.
avatar
Khawaja Saif ur Rehman Project Management Trainer & Consultant Lahore, Pakistan
Baseline = What you planned to do
Forecast = Where you see the project as of today

Baseline = forecast => Project on schedule
Baseline < forecast => Project behind schedule
Baseline > forecast => Project ahead of schedule

Schedule performance index (SPI) is a ratio of the earned value (EV) to the planned value (PV). If the SPI is less than one, it indicates that the project is potentially behind schedule to-date whereas an SPI greater than one, indicates the project is running ahead of schedule.
From: https://www.passionatepm.com/blog/schedule...-pmp-concept-40
avatar
Anonymous
Two more comments to add and clarify

1. Baseline is based on approved plan and should remain fixed throughout the project; unless there is an approved change to the project objectives.

2. The forecast is a moving estimate of the expected completion date; which maybe different than the baseline date due to performance (better or worst as Khawaja said). To calculate the forecast date we use many variables including SPI but not limited to SPI.
avatar
M. Sahir A. Shatiry, PMI-RMP, PMP Senior Hook-up and Commissioning Engineer| Petronas Carigali Sdn Bhd Ipoh, Perak Darul Ridzuan, Malaysia
The date could be the same the baseline date and forecast date. However, as all expert above mention, the baseline will be the fixed one that has been agreed and all the team will working toward the baseline target.

As such for the baseline, due certain circumstances with might provide the forecast for the best case scenario and worst case scenario for our project. For the calculation of the pert ( P+4ML+O/6) can be used for either baseline or forecast.

Please login or join to reply

Content ID:
ADVERTISEMENTS

"The secret of getting ahead is getting started. The secret of getting started is breaking your complex overwhelming tasks into small manageable tasks, and then starting on the first one."

- Mark Twain

ADVERTISEMENT

Sponsors