Difference between baseline date & forecast date Saving Changes...
Sort By:
Justin WortleyProject Manager| Quicken LoansDetroit, Mi, United States
A baseline date is a target date, and a forecast date is a best guess. Baseline is the date at which the progress is being measured, but the forecast is the best guess to what will happen in the future. Saving Changes...
Schedule performance index (SPI) is a ratio of the earned value (EV) to the planned value (PV). If the SPI is less than one, it indicates that the project is potentially behind schedule to-date whereas an SPI greater than one, indicates the project is running ahead of schedule.
From: https://www.passionatepm.com/blog/schedule...-pmp-concept-40 Saving Changes...
Anonymous
Two more comments to add and clarify
1. Baseline is based on approved plan and should remain fixed throughout the project; unless there is an approved change to the project objectives.
2. The forecast is a moving estimate of the expected completion date; which maybe different than the baseline date due to performance (better or worst as Khawaja said). To calculate the forecast date we use many variables including SPI but not limited to SPI. Saving Changes...
M. Sahir A. Shatiry, PMI-RMP, PMPSenior Hook-up and Commissioning Engineer| Petronas Carigali Sdn BhdIpoh, Perak Darul Ridzuan, Malaysia
The date could be the same the baseline date and forecast date. However, as all expert above mention, the baseline will be the fixed one that has been agreed and all the team will working toward the baseline target.
As such for the baseline, due certain circumstances with might provide the forecast for the best case scenario and worst case scenario for our project. For the calculation of the pert ( P+4ML+O/6) can be used for either baseline or forecast. Saving Changes...
"The secret of getting ahead is getting started. The secret of getting started is breaking your complex overwhelming tasks into small manageable tasks, and then starting on the first one."