Project Status Scorecard - Please let me know your view

linkedin twitter facebook   Benefits Realization   Information Technology   PMO  
avatar
Ganesh Srinivasan Ganesh PMO (PMP, PMI-SP, ITIL-F)| MNC Bank Chennai, India
Dear Members,

I'm developing a excel based scorecard, I seek your kind help for the same.

Following measurments have been taken :

Score : 5 highest satififactory , 4, 3, 2 , 1

1. Schedule - (On Track, Behind Schedule, LATE)

2. Milestones - How many crtical milestones met? (All met , More than 80% , More than 60%, Less than 40%)

3. All deliverables as per plan proceeding ( Yes, minor issues, moderate issues, serious issues,

4. Project based performance measurments given by PM's.

5. No - High Risks , High Issues ( score based on that).

Am I missing anything ? If you developed any Project scorecard , could you please help me with sample ?

Request your kind inputs. As I need produce the draft by tmw, your kind help is much appreciated :)
Sort By:
< 1 2 >
avatar
Suhail Iqbal Suhail Iqbal PMIATP CIPM FAAPM MPM MQM CLC CPRM SCT AEC SDC SMC SPOC PRINCE2 MCT| PM Training School Rawalpindi, Punjab, Pakistan
Jun 07, 2016 4:27 PM
Replying to Suhail Iqbal
...
I strip strongly agree that earned value indicators must be added.
strip was mistyping, ignore that please.
avatar
Suhail Iqbal Suhail Iqbal PMIATP CIPM FAAPM MPM MQM CLC CPRM SCT AEC SDC SMC SPOC PRINCE2 MCT| PM Training School Rawalpindi, Punjab, Pakistan
Jun 07, 2016 4:37 PM
Replying to John Caron, MBA, PMP, CSM
...
Hi Suhail, please explain...strip?
mistyped
< 1 2 >

Please login or join to reply

Content ID:
ADVERTISEMENTS

"Would you tell me, please, which way I ought to go from here?" "That depends a good deal on where you want to get to."

- Lewis Carroll

ADVERTISEMENT

Sponsors