Case: The scheduled Contract completion date of a project is going to reach in another 20 days. As per general contract condition of that particular project the client can suspend the project for 45 days. Due to some issue from client side in moving forward with the work, the client suspending the project for 45 days contractually (Prior to 20 days of scheduled completion).
Things to be clarified: 1. Suspension should be within the contract duration only? 2. How to obtain EOT without knowledge of any future works? 3. Can literally consider Contract got terminated since suspended beyond contractual completion? 4. Interim EOT possible? 5. Any relevant codes and standards to suggest for this case? Saving Changes...