Mar 13, 2017 11:21 AM
Replying to S Rajasekar
...
Go to Reports Menu - New report - Table reports - Give Name to a report
In the Right Panel - Field List - Choose Resources Tab
You will get list of resource names , start and end date for each resource allocation , So resource is allocated/engaged between these dates irrespective of number of task they are assigned , it is cumulative/duration
In the Filed List- Resources Tab - Select Work Node - Renaming Work
Now report will display resource name, Start and Finish date and remaining work
If remaining work is zero , resource is not allocated they are available
You can add this table to existing report/dashboard and also you can create custom filed to display available date using Finish + 1