which is the most effective delay analysis method for construction project? Please share your experience ..

linkedin twitter facebook   Construction   Using PMI Standards  
avatar
Mohamed basheer MOHAMED BASHEER,PMP®,PMI-SP®| Planning Manager, JASARA PMC Jeddah, Saudi Arabia
There are lot delay analysis procedures/ methods ( Like Time impact, collapsed- As built etc ) for construction , which one can be used as effective to substantiate the parties.........
Sort By:
avatar
Mohamed Ahmed Sr.Planning Engineer| Arcadis 6 October City, Ny, United States
These are some materials & tools for Delay Analysis using TIA Method (EOT Claim)
https://bibloteka.com/construction-delays-best-practices/
https://bibloteka.com/product/full-eot-claim-tia-xernarratives/
avatar
Md.Siraz Uddin Planning & Scheduling Engineer| shade corporation Ltd Dammam, Estern Provience, Saudi Arabia
well its all depend on the case in hand (i mean project situation /event status)
In general the delay analysis is categories into two major part
a.Prospective analysis (Foreword looking)
b.Retrospective (Backward looking)

In case of prospective analysis TIA is most preferred option specially when delay event is small in nature like less than reporting period..and it consider as proactive approach of delay analysis

In case of retrospective Window analysis is generally preferred as it easily enable analyst to differentiate concurrent delay..