Do you give a Milestone a WBS code?

linkedin twitter facebook   Using PMI Standards   Work Breakdown Structures (WBS)  
avatar
Kristina Marie Gjerulff Head of Business Enablement| KIRKBI Business Services Skive, Denmark
When filling out a Project Plan and developing your WBS structure, do you also give Miletones a WBS code or is this only meant for tasks?
Sort By:
avatar
Prashant Sonwane Sr. Program Manager| Winjit Technologies Pvt Ltd Nashik, Maharashtra, India
WBS is meant for tasks but we can define the milestones (based on priority decided) as well as payment terms for the project.
After accomplishment of milestones, we can release the project/products updates to the client and request milestone payment.
avatar
Kristina Marie Gjerulff Head of Business Enablement| KIRKBI Business Services Skive, Denmark
Thank you, for this project I will leave the WBS code out for Milestones, as the project is cross functional and not customer related.