How RBS & WBS are linked
Network:33



We make WBS,we also make RBS,practically RBS lower levels should somewhere flow into the main WBS
Sort By:
Network:1136



I will assume that you are talking about resource breakdown structure. You can use the WBS and the RBS to create a matrix where you can see for each wbs component the available resources to work in the component. The same you can use the WBS and the OBS to create the RAM (RACI matrix in some cases).
...
1 reply by ROHIT SHARMA
Jun 13, 2017 6:17 AM
ROHIT SHARMA
...
No Sergei,I am referring to Risk Breakdown Structure. Does anything from RBS flows to the WBS or how the RBS remains an isolated document
Network:1036



I concur with Sergio.
Network:101



Rohit, I am assuming you are making the RBS and WBS in a non-MS project template somewhere. If you are using MS project, it happily and seamlessly makes both at the same time as long as you use the resource template within MS project. Otherwise, whatever Sergio suggested is the best way to integrate both.
...
1 reply by ROHIT SHARMA
Jun 13, 2017 6:19 AM
ROHIT SHARMA
...
Hi Deepa, I am referring to Risk Breakdown Structure,whether you connect the RBS..WBS dots somewhere or RBS remains isolated
Network:33



Jun 12, 2017 10:41 AM
Replying to Sergio Luis Conte
...
I will assume that you are talking about resource breakdown structure. You can use the WBS and the RBS to create a matrix where you can see for each wbs component the available resources to work in the component. The same you can use the WBS and the OBS to create the RAM (RACI matrix in some cases).
No Sergei,I am referring to Risk Breakdown Structure. Does anything from RBS flows to the WBS or how the RBS remains an isolated document
...
1 reply by Sergio Luis Conte
Jun 13, 2017 8:07 AM
Sergio Luis Conte
...
Then, there is no link between them. Both are totally different structures to be use for different things.
Network:33



Jun 13, 2017 12:46 AM
Replying to Deepa Kalangi
...
Rohit, I am assuming you are making the RBS and WBS in a non-MS project template somewhere. If you are using MS project, it happily and seamlessly makes both at the same time as long as you use the resource template within MS project. Otherwise, whatever Sergio suggested is the best way to integrate both.
Hi Deepa, I am referring to Risk Breakdown Structure,whether you connect the RBS..WBS dots somewhere or RBS remains isolated
Network:1136



Jun 13, 2017 6:17 AM
Replying to ROHIT SHARMA
...
No Sergei,I am referring to Risk Breakdown Structure. Does anything from RBS flows to the WBS or how the RBS remains an isolated document
Then, there is no link between them. Both are totally different structures to be use for different things.
Network:2471



Yep Risk is different and should be managed in a risk matrix of its own.
Network:33



When you Breakdown Risks to actionable level after Risk response,something should come into WBS from that,let's say you choose Reduce then Activity to reduce it ...shouldn't that become part of WBS