Baselines would be updated with any significant change - significant is understandably subjective, but one would have to use their best judgement.
For example, if my project gets bumped down the priority ladder, with revised durations, or if there is an excepted change request, I will re-baseline. That said, you don't necessarily have to update the original. I recommend saving under the other options, baseline1, baseline2, etc. This gives you the ability to then add multiple baselines to the reports to provide a visual effect of the impacts - positive or negative.