Change Request Pass Through CCB Board & Came from Execution & Planning Process Pass Through Monitor & Control With Change Control Board May be Approved or not & tracked In Change Log Either Approved or not , On The other Hand Approved change Request O/P From Control Process & Performed in execution process & Lead to updating all Plans & Base Lines After that Inform All Stack holders AAbout Change that may be defec repair or corrective action Or Update. Saving Changes...
Deepesh RammoorthyICT Project Manager ( PMP®AgilePM®Certified ScrumMaster® (CSM®))| Australian Red Cross Blood ServiceTarneit, Vic, Australia
A change request can originate from any of the Monitoring and Controlling processes and Most of the Executing processes. A change request can be a Defect repair, a corrective action or a preventive action A change request could impact the Baselines - Cost, Schedule and Scope and therefore needs to be analysed for it's Impact on the different project constraints - The triple constraints plus Quality, Human Resources, Communications, Risks, Procurements. The Changes MUST pass through Integrated Change Control in order to avoid Scope Creep , Traceability through the Project Life Cycle and maintenance of the Integrity of the Baselines.
Until the Change Control Board approves it , the change is simply a Change Request . The Integrated Change Control Process , results in Approved Change Requests and a Log of Change Requests (Change Log), whether approved or Rejected , which need to be communicated to the stakeholders via "MANAGE STAKEHOLDER ENGAGEMENT"
Approved Change Requests are inputs to Direct and Manage Project Work Plan Procurement Management Control Quality - which has a tool and technique called as Approved Change Requests Review .....The output is Validated Changes . What Control Quality is essentially doing is checking if the Preventive Action , Corrective action or the Defect Repair has been performed appropriately and if the change has been validated. Once the change has been validated , the PMP is updated, any relevant project documents are updated, the Performance Measurement Baseline is readjusted (time, cost, scope). The project manager then continues project delivery according to the new adjusted baseline. Saving Changes...
A Change Request may or may not be approved. Approved Change Requests were already approved and can be actioned in Direct and Manage Project Work. Saving Changes...
LORI WILSONRETIRED - Technical Project Manager| RETIRED - LifePoint HealthClarkston, Wa, United States
Hello George - You like to make us think! I agree with my colleagues on this one. Change Requests are submitted to a governing body. At my company, it is the CAB (Change Advisory Board). This governing body approved the Change Requests. Saving Changes...