Project Premature Closure

linkedin twitter facebook   Lessons Learned  
avatar
Sandeep Thoppil Chief Technology Officer| CBS Botswana Gaborone, South East, Botswana
As project manager what all things should we commit if any of the party stops further execution of the project? What possible impact will such a termination cause to the PM? As a PM what all possible risks I should face later if I plan to quit my job before a project closure? Post your valuable comments or contact me [email protected].
Sort By:
avatar
Anonymous
Saneep, You put two big question I will try to answer one question and I not sure about the other. When party stop execution of the project prematurlly, is it because of business decision or is it becuase bad project delivery?. If it is business decision then PM not thing to worry about, and if it is becuase bad project deliverable then PM is accounted for every thing. So I hope it is the first case you talking about.
avatar
Sandeep Thoppil Chief Technology Officer| CBS Botswana Gaborone, South East, Botswana
The project closed because of Client's business decission. How to bill the client for resources locked for the project and other expenses.
avatar
Tom Welch PMP Mesa, Az, United States
This sort of situation should have been covered by the contract agreement you sign, that's your starting point.

Please login or join to reply