Project Management

Please login or join to subscribe to this thread

Working with project team

linkedin twitter facebook   Business Intelligence   Leadership   Resource Management   Strategy  
avatar
Anish Abraham Privacy Program Manager| University of Washington Auburn, Wa, United States
A project may require skills that the project team do not possess. As a project manager it is our responsibility to determine the needed competencies, assess the available staff and recommend training. In this scenario, a software developer is new to a particular technology and at the start of a project it i was assumed that this person will be able to come up to speed with a little or no training. But when the project is started it becomes very obvious that the project may need an expert since the developer won't be able to finish the work on time. When the PM reached out to the project sponsor, somehow this person seems to be unresponsive due to political reasons. What is the best thing the project manager can do in this situation?
Sort By:
avatar
Deepesh Rammoorthy ICT Project Manager ( PMP®AgilePM®Certified ScrumMaster® (CSM®))| Australian Red Cross Blood Service Tarneit, Vic, Australia
The Project Manager must do the ground work and needs to put down the analysis in writing as a paper to be presented to the project steering committee. It's not a naming and shaming exercise. It's the facts as clearly as they come:-

What is the skill-set that was being sought in the project ?
What was the skill-set available in house?
What was the rationale behind up-skill of the in-house staff? perhaps to keep proprietary information in-house, to increase internal capabilities, to align with organizational practices , etc
What was done to train and bring the in house staff upto speed?
What is the current situation and analysis?
What is the proposed? E.G . go to the market and find a suitable software engineer.
What is the market research? Software engineer will cost x dollars per hour and will take x amount of time to finish the project.
An analysis must also be done for the fact that if the in-house staff is able to be trained and is able to complete the work , it may take x amount of time more than an external resource.

after all the facts are presented, the Project Manager must recommend an option , which in this case will be - hiring the external resource to finish the work on time.

This may be a change request to the project and will therefore need the budget to be adjusted and additional funds required for external new software engineer or it could be increased training and more time required to finish the project.

the steering committee may direct you one way or the other according to the facts presented and the sponsor is not the only person making the decision.

The ball is in their court and whatever decision is made, the PM then abides by it.
...
1 reply by Anish Abraham
Dec 09, 2017 6:52 PM
Anish Abraham
...
Thanks Deepesh for the detailed feedback on this.
avatar
Anish Abraham Privacy Program Manager| University of Washington Auburn, Wa, United States
Dec 09, 2017 5:54 PM
Replying to Deepesh Rammoorthy
...
The Project Manager must do the ground work and needs to put down the analysis in writing as a paper to be presented to the project steering committee. It's not a naming and shaming exercise. It's the facts as clearly as they come:-

What is the skill-set that was being sought in the project ?
What was the skill-set available in house?
What was the rationale behind up-skill of the in-house staff? perhaps to keep proprietary information in-house, to increase internal capabilities, to align with organizational practices , etc
What was done to train and bring the in house staff upto speed?
What is the current situation and analysis?
What is the proposed? E.G . go to the market and find a suitable software engineer.
What is the market research? Software engineer will cost x dollars per hour and will take x amount of time to finish the project.
An analysis must also be done for the fact that if the in-house staff is able to be trained and is able to complete the work , it may take x amount of time more than an external resource.

after all the facts are presented, the Project Manager must recommend an option , which in this case will be - hiring the external resource to finish the work on time.

This may be a change request to the project and will therefore need the budget to be adjusted and additional funds required for external new software engineer or it could be increased training and more time required to finish the project.

the steering committee may direct you one way or the other according to the facts presented and the sponsor is not the only person making the decision.

The ball is in their court and whatever decision is made, the PM then abides by it.
Thanks Deepesh for the detailed feedback on this.
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
At least you have a steering committee. It should be fairly straightforward to present the impact of the inexperienced developer on the project (ie. time), and then you can put together the justification for an expert to speed things up, at additional cost. This will come down to if either the schedule or budget constraint is more important.
...
1 reply by Anish Abraham
Dec 10, 2017 11:49 AM
Anish Abraham
...
In this case there is no steering committee in place, so will have to try some other alternative. Thanks Sante, for your valuable comments.
avatar
Mansoor Mustafa Senior PM| Government Department Rawalpindi Punjab, Pakistan
Agree with Deepesh it PM to provide analysis of ground work and if he thinks some resource is not have capacity to perform as per the requirement of project and because of this project may be suffered so he acquire new resource from internal from organization or externally through CCB.
...
1 reply by Anish Abraham
Dec 10, 2017 11:49 AM
Anish Abraham
...
Thanks Mansoor for your comments.
avatar
Anish Abraham Privacy Program Manager| University of Washington Auburn, Wa, United States
Dec 10, 2017 1:59 AM
Replying to Sante Delle-Vergini, PhD
...
At least you have a steering committee. It should be fairly straightforward to present the impact of the inexperienced developer on the project (ie. time), and then you can put together the justification for an expert to speed things up, at additional cost. This will come down to if either the schedule or budget constraint is more important.
In this case there is no steering committee in place, so will have to try some other alternative. Thanks Sante, for your valuable comments.
avatar
Anish Abraham Privacy Program Manager| University of Washington Auburn, Wa, United States
Dec 10, 2017 2:12 AM
Replying to Mansoor Mustafa
...
Agree with Deepesh it PM to provide analysis of ground work and if he thinks some resource is not have capacity to perform as per the requirement of project and because of this project may be suffered so he acquire new resource from internal from organization or externally through CCB.
Thanks Mansoor for your comments.
avatar
Abdisahal Ahmed Burao, Togdheer, Somalia
thanks all
I am just learning I am very new
...
1 reply by Anish Abraham
Dec 27, 2017 11:38 AM
Anish Abraham
...
Thanks Abdisahal.
avatar
Anish Abraham Privacy Program Manager| University of Washington Auburn, Wa, United States
Dec 27, 2017 8:27 AM
Replying to Abdisahal Ahmed
...
thanks all
I am just learning I am very new
Thanks Abdisahal.

Please login or join to reply

Content ID:
ADVERTISEMENTS

"The only way to keep your health is to eat what you don't want, drink what you don't like and do what you'd rather not."

- Mark Twain

ADVERTISEMENT

Sponsors