Project Management

Please login or join to subscribe to this thread

Control accounts

linkedin twitter facebook   Work Breakdown Structures (WBS)  
avatar
Abdulrahman Abuhayah P.M.O Director| Adaptive TechSoft Riyadh, Riyadh, Saudi Arabia
Hellow everyone,
Can you please elaborate more about what a control account is in a WBS?
what is the relationship between work packages and control accounts, in other words, is it one to one relation or one to many or many to many or many to one...etc?
is it a must to have control accounts? when to have them? why have control account?
Sort By:
< 1 2 >
avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Also the organization, PMO or program/portfolio manager may and probably will stipulate where you must have control accounts placed in the WBS.
avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
Feb 13, 2018 5:23 AM
Replying to Kevin Drake
...
work packages are connected to one control account, but it cannot be connected to more than one control account. The control account will have few work packages.
Very good explanation, well done
avatar
Sebastian Singer CISO| Thuringia Court of Auditors Germany
Feb 13, 2018 8:39 AM
Replying to Kiron Bondale
...
Abdulrahman -

1. Correct
2. No - the term work package denotes the lowest level of a WBS branch
3. Management reserve will not be part of the control account - it normally is reflected as a project-wide allocation (or sometimes even managed at a portfolio level).
4. Correct

Kiron
Thank you for your explanation in No. 2: this was an eye opener.
avatar
Michael Delaney Partner| Delaney Management LLC West Chester, Pa, United States
Very thorough explanation, thanks
avatar
meisam mehrvarzi Project Planning & control Engineer| Mapna Sari, Iran (Islamic Republic of)
Feb 13, 2018 5:21 AM
Replying to Kevin Drake
...
Control Account vs Work Package


Once the project scope is divided in the form of WBS, work packages, and activity level, it is time to track 2whether a project is reaching its milestones. However, it is very difficult to track a project at a very high level or at the lowest level (the lowest level is the activity level).

So, in order to to manage the project better, we take a point between the WBS and work package call it the Control Account.

Control Account is a management control point where scope, cost, and schedule are integrated and compared to the earned value for performance measurement. Control Accounts are placed at selected management points in the WBS. Each Control Account is defined with a unique code or an accounting number which can be used to link to the performing account system.

The ‘Work Package’ is a deliverable which is obtained after decomposing the WBS. Work packages are further divided into activity levels. A Control Account usually has one or more work packages. The following figure explains the relations or the hierarchy in which each of the components is placed.

When doing Earned Value Management within a standard project structure there can be a defined level that is considered a "control account". A control account is normally the intersection of the functional organization doing the work and the Project organizational hierarchy. This is typically defined as the level that you can aggregate BCWS, BCWP, and Actuals AND is a level that is controlled by a single organization. Below a control account is a "Work Package". The work package is the level of the project that the user plans and a takes status on for EV.

Below is the general hierarchy concept of organizing and maintaining a control account or work package:
• A work package is BELOW a control account. However, it does not have to be directly below a control account.
• You cannot have a control account below another control account.
• You cannot have a work package below another work package.
• Management Reserve and Undistributed Budget cannot be part of the control account hierarchy. In other words
o Cannot be an object that has a Control Account defined BELOW it.
o Cannot be an object that has a Control Account defined ABOVE it.

Once the project structure is defined into control accounts and work packages responsibility and ownership can now be established. This requires assigning Control Account Managers or CAMs to play an essential role in Earned Value Management. They are responsible for the planning, coordination, and achievement of all work within a control account. They also provide authorization for all scope, technical and cost changes for their respective control accounts.
Very usefull , Thank u Kevin.
< 1 2 >

Please login or join to reply

Content ID:
ADVERTISEMENTS

"There are painters who transform the sun into a yellow spot, but there are others who, with the help of their art and their intelligence, transform a yellow spot into the sun."

- Pablo Picasso

ADVERTISEMENT

Sponsors