How would you answer this question on the PMP exam only given the following information?
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
a. 4
b. 5
c. 6
d. 7
Trying to understand which PMI prefers when the formula to use is not provided. I missed this question on a practice exam and would like to avoid doing this on the real exam.
There are 2 possible correct answers, 6 if using beta, 7 if using triangular. Saving Changes...
Sort By:
Dinah YoungProject Manager / Software Asset Manager| Prince William CountySpringfield, Va, United States
If it is not specified, use the PERT formula (O + 4(M) + P / 6. So the answer would be c Saving Changes...
Dinah's right - a PERT, beta distribution or weighted average should be the default choice unless they specify the triangular distribution in the body of the question.