Project Management

Please login or join to subscribe to this thread

Triangular or Beta Formula. Which estimation formula to use?

linkedin twitter facebook   Cost Management   Schedule Management   Scheduling   Using PMI Standards  
avatar
Dwayne Arnold Buford, Ga, United States
How would you answer this question on the PMP exam only given the following information?

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

a. 4
b. 5
c. 6
d. 7


Trying to understand which PMI prefers when the formula to use is not provided. I missed this question on a practice exam and would like to avoid doing this on the real exam.

There are 2 possible correct answers, 6 if using beta, 7 if using triangular.
Sort By:
avatar
Dinah Young Project Manager / Software Asset Manager| Prince William County Springfield, Va, United States
If it is not specified, use the PERT formula (O + 4(M) + P / 6. So the answer would be c
avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Dinah's right - a PERT, beta distribution or weighted average should be the default choice unless they specify the triangular distribution in the body of the question.

Kiron
avatar
Dwayne Arnold Buford, Ga, United States
Thanks! Much appreciated!
avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
Dinah's your new RMP in application :-)

For the triangular, if i remember well it use when talking about software project in the context of the PMP exam.

Please login or join to reply

Content ID:
ADVERTISEMENTS

"Whatever does not destroy me makes me stronger."

- Friedrich Wilhelm Nietzsche

ADVERTISEMENT

Sponsors