How would you answer this question on the PMP exam only given the following information?
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
a. 4
b. 5
c. 6
d. 7
Trying to understand which PMI prefers when the formula to use is not provided. I missed this question on a practice exam and would like to avoid doing this on the real exam.
There are 2 possible correct answers, 6 if using beta, 7 if using triangular. Saving Changes...
Sort By:
Dinah YoungProject Manager / Software Asset Manager| Prince William CountySpringfield, Va, United States
If it is not specified, use the PERT formula (O + 4(M) + P / 6. So the answer would be c Saving Changes...
Dinah's right - a PERT, beta distribution or weighted average should be the default choice unless they specify the triangular distribution in the body of the question.
"You can make more friends in two months by becoming interested in other people than you can in two years by trying to get other people interested in you."