Utkarsh Ajay ShahAssistant Manager| L&T Hydrocarbon Engineering Ltd.Mumbai, Maharahstra, India
Positive risks do not necessarily increase the contingency reserve and going strictly by theory it actually deducts from the existing contingency risk reserve calculation. (please refer RIta Mulcahy 9th edition for examples) .
Many times for positive risks which are time bound opportunities, a contingency plan is drawn up and kept ready to be put in execution if the risk pops up. Sometimes, the project team may work in a way to initiate the pop up so as to grab the opportunity. Saving Changes...