Reduce risk by enhancing estimation

From the Easy in theory, difficult in practice Blog
by
My musings on project management, project portfolio management and change management. I'm a firm believer that a pragmatic approach to organizational change that addresses process & technology, but primarily, people will maximize chances for success. This blog contains articles which I've previously written and published as well as new content.

About this Blog

RSS

Recent Posts

Leading Through Crisis Means Leading Through Context

"It's the end. But the moment has been prepared for." - retirement lessons from the Doctor

Just because they are non-critical, doesn't mean they are not risky!

Just because they are non-critical, doesn't mean they are not risky!

How will YOU avoid these AI-related cognitive biases?

Categories

Agile, Artificial Intelligence, Career Development, Change Management, Communications Management, Decision Making, Governance, Hiring, Kanban, Lessons Learned, Personal Development, PMO, Portfolio Management, Project Management, Resource Management, Risk Management, Risk Management, Schedule Management, Scheduling, Tools

Date

linkedin twitter facebook Request to reuse this  


I’ve frequently said that project management is about bringing predictability to uncertainty and while a lot of my writing focuses on managing the impacts of uncertainty through effective risk management, estimation is another area where uncertainty needs to be addressed.

If you are fortunate enough to be managing projects where sufficient historical data exists to account for nearly all sources of variation then I envy you.

For the rest of us, here are some estimation principles which should be applicable regardless of the project’s domain or specific context.

  • Use more than one estimation method: Consider this a form of hedging your bets. If you derive close to the same estimated value using different techniques, the likelihood that your estimates are significantly incorrect drops. Consider combining bottom-up and top-down methods.
  • Document and share assumptions related to the estimates: It’s always a good idea to have a second pair of eyes review estimates, but without understanding the underlying assumptions which those estimates were based on, it can be very difficult to provide quality feedback. If the assumptions are not documented, it eliminates your ability to identify proactively when internal or external changes might invalidate the assumptions & their associated estimates.
  • An estimate should never be provided as a single value: Without some understanding of the variation in the stated estimate, it’s impossible to manage the uncertainty resulting from it. This variation could be stated as a range or a confidence level.
  • Discourage multitasking during estimation: Estimation takes significant mental effort and if the subject matter experts involved are distracted, the quality of your estimates will suffer.  Consider breaking up the estimation process into more short meetings as one way to overcome this.  Also, avoid estimation right after lunch time or at the end of the working day as your team might be less focused.
  • Evaluate estimates across multiple dimensions: Just as it is helpful to use more than one estimation technique, it’s also valuable to analyze estimates in different ways to try to identify flaws. For example bottom-up activity estimation will give us detailed effort data at the work package level. But aggregating these estimates by resource role or by project phase will enable us to evaluate whether the ratio between roles or phases is logical.
  • Remove the person from the evaluation: It helps to have peer-level reviews of estimates without knowing who produced them. This sounds wrong, but no subject matter expert is omniscient and our positive biases about them might cause us to unconsciously miss estimation flaws.

Improving estimation is not a silver bullet to slay all sources of project schedule or cost variation but elevating project management capability is about evolution, not revolution!

(Note: this article was originally accurately estimated and risk reduced in July 2014 on kbondale.wordpress.com)


Posted on: October 11, 2018 06:59 AM | Permalink

Comments (22)

Page: 1 2 <prev

Please login or join to subscribe to this item
avatar
Jo Ann Noel Project Manager| Ministry of Planning El Dorado, Trinidad and Tobago
Good article. some interesting points raised.

avatar
Ravi Advani VP, Partner Solutions| Vbrick Systems Chattanooga, Tn, United States
Good advice, Kiron! I especially liked the last bullet "Remove the person from the evaluation" - that's a great way to reduce variance in the cost of the work performed by applying a different skill to generating the estimate vs. actual work performed.

Page: 1 2 <prev

Please Login/Register to leave a comment.

ADVERTISEMENTS

"Nearly every great advance in science arises from a crisis in the old theory, through an endeavor to find a way out of the difficulties created. We must examine old ideas, old theories, although they belong to the past, for this is the only way to understand the importance of the new ones and the extent of their validity."

- Albert Einstein

ADVERTISEMENT

Sponsors