Project Management

Please login or join to subscribe to this thread

Padding: Is this really a "Professional Option" ?

linkedin twitter facebook   Estimating   Risk Management   Scheduling   Using PMI Standards   Work Breakdown Structures (WBS)  
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
As you all know, Padding is basically adding extra time or cost to an estimate because the estimator does not have enough information.

Have you ever considered padding in your project estimates and why ?
Sort By:
< 1 2 3 4 5 6 7 8 9 >
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Sep 08, 2016 1:29 PM
Replying to Mayte Mata Sivera
...
First of all, I need to say that I find the padding a bad practice, but I'll write down a situation to reactivate this interesting subject.

Situation

PM - Project Manager
T - Technician
AM - Account Manager

PM – Ask to technician the time that he/she needs to make a development.

T - Really need 1.5 days but he thinks that maybe he will find some issues (lack of information) then he tells to the PM 2 days.

PM - analyzes the data and includes +0.5 buffer or contingency, (As a PM we aren’t all subject mater experts…then is really a buffer or is a lack of information?)

AM - +0.5 benefits.

The client will receive a proposal for 3 days.

For all of us, is crystal clear that the account manger that he/she is doing properly and ethically their job. Benefits are benefits and all companies need to get it.

But why all us think that the Technician is padding?

From my point of view and based in my experience, best tool to avoid this kind of situations is communication and confidence or trust between the project manager and their team.
Good Example Maria - Thanks for sharing your thoughts.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Sep 08, 2016 8:08 AM
Replying to Sergio Luis Conte
...
First of all, as far as I know, "padding" is not in the PMI vocabulary/lexicon/standards neither in other organizations related with project management. Second, the use of padding, because there is not explicit calculation method or formulas about that, adds more risk to the whole project because the inherent uncertainty (not calculated) has padding. Third, because there is no formal definition people usually confuse padding with buffers. Fourth, you allways are using a formula, explicit or implicit, to calculate extra time in your project. Just in case of implicit then it is based on your experience and is the moment where you are adding extra "something". If you have no enough information then you allways will do that. Think about your personal life. The problem here is when you do not manage it. It is catastrophic.
Hi Sergio,

Thanks for sharing your opinion - I agree with your explanation. However, I got to know about padding while I was studying for my PMP so padding is mentioned somewhere in the PMI and explained in details in Rita's Book.
avatar
Scott Sale Program Manager| Kindred Louisville, Ky, United States
Sep 08, 2016 1:29 PM
Replying to Mayte Mata Sivera
...
First of all, I need to say that I find the padding a bad practice, but I'll write down a situation to reactivate this interesting subject.

Situation

PM - Project Manager
T - Technician
AM - Account Manager

PM – Ask to technician the time that he/she needs to make a development.

T - Really need 1.5 days but he thinks that maybe he will find some issues (lack of information) then he tells to the PM 2 days.

PM - analyzes the data and includes +0.5 buffer or contingency, (As a PM we aren’t all subject mater experts…then is really a buffer or is a lack of information?)

AM - +0.5 benefits.

The client will receive a proposal for 3 days.

For all of us, is crystal clear that the account manger that he/she is doing properly and ethically their job. Benefits are benefits and all companies need to get it.

But why all us think that the Technician is padding?

From my point of view and based in my experience, best tool to avoid this kind of situations is communication and confidence or trust between the project manager and their team.
Agree, This is a very common and a good example to illustrate.
avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
First let say that any amount (time or money) put for contingency and risk reserve should be calculated.
When people in the team put padding (unexpected) it add to the proposal cost of the project making it less competitive. I've seen case where padding was put on top of an other unknown padding. Making the projet a no go.
So padding is not an option.
...
1 reply by Rami Kaibni
Sep 09, 2016 1:18 AM
Rami Kaibni
...
Good Example Vincent, thanks for sharing.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Sep 08, 2016 10:37 PM
Replying to Vincent Guerard
...
First let say that any amount (time or money) put for contingency and risk reserve should be calculated.
When people in the team put padding (unexpected) it add to the proposal cost of the project making it less competitive. I've seen case where padding was put on top of an other unknown padding. Making the projet a no go.
So padding is not an option.
Good Example Vincent, thanks for sharing.
avatar
Predrag Pancic Head of Payment card department| Erste Bank AD Podgorica Podgorica, Montenegro
I must say that I very much like this tread as it is full of excellent information's.
As I see it best way to prevent padding is proper and open communication within project team. Communication is the key and I get that.

Since estimation is (usually) done by process experts I would like to know how can you, based on your experience, effectively identify and fight or maybe its better to say manage padding?
Do you, as PMs, ask to be provided methodology of delivered estimate or...?

Thanx.
...
1 reply by Rami Kaibni
Dec 05, 2016 8:29 PM
Rami Kaibni
...
Thanks for your input Predrag.

To answer your question, padding should not exist at all so you do not need to know how to manage it. From my point of view, padding is a NO-NO Situation.

We as PM's should participate in Estimates at least during planning phase so we are aware what is going on.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Dec 05, 2016 5:07 PM
Replying to Predrag Pancic
...
I must say that I very much like this tread as it is full of excellent information's.
As I see it best way to prevent padding is proper and open communication within project team. Communication is the key and I get that.

Since estimation is (usually) done by process experts I would like to know how can you, based on your experience, effectively identify and fight or maybe its better to say manage padding?
Do you, as PMs, ask to be provided methodology of delivered estimate or...?

Thanx.
Thanks for your input Predrag.

To answer your question, padding should not exist at all so you do not need to know how to manage it. From my point of view, padding is a NO-NO Situation.

We as PM's should participate in Estimates at least during planning phase so we are aware what is going on.
avatar
Predrag Pancic Head of Payment card department| Erste Bank AD Podgorica Podgorica, Montenegro
I understand that and must say that I agree but we do live in imperfect world.
...
1 reply by Rami Kaibni
Dec 06, 2016 11:13 AM
Rami Kaibni
...
This is a very true statement - At least we do our best to do our work as close to perfect as possible.
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
Dec 06, 2016 11:11 AM
Replying to Predrag Pancic
...
I understand that and must say that I agree but we do live in imperfect world.
This is a very true statement - At least we do our best to do our work as close to perfect as possible.
avatar
Vincent Guerard Coach - Trainer - Speaker - Advisor| Freelance Mont-Royal, Quebec, Canada
Jan 09, 2016 12:02 AM
Replying to Suhail Iqbal
...
I agree with Rami, Padding is NOT Contingency. Where adding reserves and contingencies is a fairly logical and acceptable choice in project management, padding is that CRIMINAL ACT which must be abhorred and avoided by all project managers. Padding means unreasonably and thoughtlessly adding illogical additions to cost or duration. Reserves and contingencies have a logical and official reasoning, or even statistics to prove it right. I would say PADDING IS NOT ALLOWED.
< 1 2 3 4 5 6 7 8 9 >

Please login or join to reply

Content ID:
ADVERTISEMENTS

"To stimulate creativity, one must develop the childlike inclination for play and the childlike desire for recognition."

- Albert Einstein

ADVERTISEMENT

Sponsors