Project Management

Please login or join to subscribe to this thread

What's the most difficult question you've faced in a mock exam?

linkedin twitter facebook   Information Technology   New Practitioners   Scheduling   Work Breakdown Structures (WBS)  
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
What's the most difficult question you've faced in a mock exam?

It could be a general topic
It could be a knowledge area
It could be a process group
It could be a particular question that you never got by
It could be a phrase/wording

I want to hear from your experiences...
Sort By:
< 1 2 3 4 5 6 7 8 9 10 >
avatar
NGUEDIA Bernis Functional Manager| VIETTEL CAMEROUN S.A. Douala, Coastal, Cameroon
All questions can be challenging... depending on how good one can be with the topic or the concept covered by the question
...
1 reply by George Lewis
Jun 01, 2016 5:43 AM
George Lewis
...
NGUEDIA - that's correct, but there is always a questions that haunts you all the way tr your study plan...

Do you have one of those you can share?
avatar
Shailja Jindal Senior Consultant| Capgemini Faridabad, Haryana, India
All and none is tricky.
avatar
Urvashi Sharma Project's Portfolio Manager - IT Infrastructure| IBM Bangalore, Karnataka, India
I got 80% of questions on Change management, and it was really tricky. spleacially Questions having "NOT the right option" , Comunication channel questions , where you tend to forget that you need to count youself too to get the right number of channels
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
May 30, 2016 3:24 AM
Replying to NGUEDIA Bernis
...
All questions can be challenging... depending on how good one can be with the topic or the concept covered by the question
NGUEDIA - that's correct, but there is always a questions that haunts you all the way tr your study plan...

Do you have one of those you can share?
avatar
Neil Frechette Global IT Manager| Farmers Edge Inc Winnipeg, Manitoba, Canada
For me, it is the questions that appear (at first) to have nothing to do with your exam. Like this sample exam question;
A production process has been defined as part of an industrial equipment manufacturing project. The process is intended to produce steel bolts with a length of 20 cm.
The control limits are 19.955cm and 20.045cm.

The measurements made at the end of the process yielded the following results:
20.033cm, 19.982cm, 19,995cm, 20.006cm, 19.970cm, 19.968cm, 19.963cm, 19.958cm, 19.962cm, 19.979cm, 19.959cm.

What should be done?
A)The process is under control. It should not be adjusted.
B)A special cause should be investigated, the process should be adjusted.
C)The control limits should be adjusted.
D)The measuring equipment should be recalibrated.
...
3 replies by Aman Soni, George Lewis, and Rody Nigel
Jun 09, 2016 11:43 AM
George Lewis
...
Neil - I won't even bother asking for the answer... :)
Jun 10, 2016 7:33 AM
Aman Soni
...
Hi, Mr. Frechette,
I think below is the correct answer as for already defined control limits are 19.955cm and 20.045cm, & all observations are in limit and as desired. So, why to do more analysis.
1)The process is under control. It should not be adjusted. (It is a correct answer)
Aug 04, 2016 11:23 AM
Rody Nigel
...
The trick here is that is not more than six consécutives measurements should be either below or above the mean. In the présent case, we have more than six consécutives measurements below the mean 20. So the production is out of control.

This question is related to pmp and quality control
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
Jun 07, 2016 10:57 AM
Replying to Neil Frechette
...
For me, it is the questions that appear (at first) to have nothing to do with your exam. Like this sample exam question;
A production process has been defined as part of an industrial equipment manufacturing project. The process is intended to produce steel bolts with a length of 20 cm.
The control limits are 19.955cm and 20.045cm.

The measurements made at the end of the process yielded the following results:
20.033cm, 19.982cm, 19,995cm, 20.006cm, 19.970cm, 19.968cm, 19.963cm, 19.958cm, 19.962cm, 19.979cm, 19.959cm.

What should be done?
A)The process is under control. It should not be adjusted.
B)A special cause should be investigated, the process should be adjusted.
C)The control limits should be adjusted.
D)The measuring equipment should be recalibrated.
Neil - I won't even bother asking for the answer... :)
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
Any more examples?
avatar
Partha S. Ghose, PMP Director - Projects| Kalyani Steels Limited Navi Mumbai, Maharashtra, India
Stakeholder related question for a project in foreign land in an unknown environment
...
1 reply by George Lewis
Jun 10, 2016 6:37 AM
George Lewis
...
Partha, interesting... Do you have a specific example?
avatar
George Lewis Program/Project Manager| DXC Technology Company Heredia, Costa Rica
Jun 10, 2016 12:13 AM
Replying to Partha S. Ghose, PMP
...
Stakeholder related question for a project in foreign land in an unknown environment
Partha, interesting... Do you have a specific example?
avatar
Aman Soni Sales and Application Manager| M/s Camfil India Pvt. Ltd. India
Jun 07, 2016 10:57 AM
Replying to Neil Frechette
...
For me, it is the questions that appear (at first) to have nothing to do with your exam. Like this sample exam question;
A production process has been defined as part of an industrial equipment manufacturing project. The process is intended to produce steel bolts with a length of 20 cm.
The control limits are 19.955cm and 20.045cm.

The measurements made at the end of the process yielded the following results:
20.033cm, 19.982cm, 19,995cm, 20.006cm, 19.970cm, 19.968cm, 19.963cm, 19.958cm, 19.962cm, 19.979cm, 19.959cm.

What should be done?
A)The process is under control. It should not be adjusted.
B)A special cause should be investigated, the process should be adjusted.
C)The control limits should be adjusted.
D)The measuring equipment should be recalibrated.
Hi, Mr. Frechette,
I think below is the correct answer as for already defined control limits are 19.955cm and 20.045cm, & all observations are in limit and as desired. So, why to do more analysis.
1)The process is under control. It should not be adjusted. (It is a correct answer)
...
1 reply by Rody Nigel
Aug 04, 2016 11:33 AM
Rody Nigel
...
If more than 6 consecutive measurements are below or above the mean, then the process is out of control. This is called The Rule of Seven. Its a very relevant PMP question
< 1 2 3 4 5 6 7 8 9 10 >

Please login or join to reply

Content ID:
ADVERTISEMENTS
ADVERTISEMENT

Sponsors