Do you typically organize your project plan according to the project life cycle, process groups or some other way?

linkedin twitter facebook   Organizational Project Management   Resource Management   Service Management   Work Breakdown Structures (WBS)  
avatar
Gail Kaufman Retired (former project manager) CT, United States
I am a project manager on the implementation services team of a company that delivers relocation services, and am in the process of reworking my team's project plan template. Currently, it is broken out by work streams such as technology, service delivery design, financial services, etc. Within each work stream, the five process groups apply (initiating, planning, executing, monitoring and controlling, and closing). My goal is to design a template that is more linear and sequential, and I am leaning toward a breakdown according to process group. This may make it easier to follow, and also help with logging hours in preparation of the PMP exam, which requires such a breakdown. How is your project plan broken out?
Sort By:
< 1 2 >
avatar
Rami Kaibni
Community Champion
Senior Projects Manager | Field & Marten Associates New Westminster, British Columbia, Canada
From what you've mentioned, it seems your project is a multi-phase project. Each phase should go through the 5 process groups in sequence of course as I assume they are related (Phase 2 can't start before Phase 1 is complete ?)
...
1 reply by Gail Kaufman
Nov 11, 2016 2:08 PM
Gail Kaufman
...
Thanks, Rami. It sounds like I'm on the right track then. Each project (implementation) includes multi-phase work streams, so I am listing the associated processes within the relevant process groups. As a simplified example, for one type of service, the PMs need to conduct data gathering and understand the client structure (initiating) before they can align with the client on the approach (planning) and then create the appropriate communications (executing).
avatar
NOHELY COLINA Lider de Proyecto| PETROPIAR Lecheria, Anzoategui, Venezuela (Bolivarian Republic of)
Yes I do, For IT Pojects We used a preliminary template disaggregated by groups of processes and then adjusted according to the particularity of the project.
...
1 reply by Gail Kaufman
Nov 11, 2016 2:08 PM
Gail Kaufman
...
Thanks, Nohely!
avatar
Anupam India
yes sometimes, based on the requirement
...
1 reply by Gail Kaufman
Nov 11, 2016 2:09 PM
Gail Kaufman
...
Thanks, Anupam!
avatar
Mayte Mata Sivera PMO Leader | Speaker | Author Ut, United States
Yes, usually for IT we do.
...
1 reply by Gail Kaufman
Nov 11, 2016 2:09 PM
Gail Kaufman
...
Thanks, Maria!
avatar
Gail Kaufman Retired (former project manager) CT, United States
Nov 11, 2016 11:42 AM
Replying to Rami Kaibni
...
From what you've mentioned, it seems your project is a multi-phase project. Each phase should go through the 5 process groups in sequence of course as I assume they are related (Phase 2 can't start before Phase 1 is complete ?)
Thanks, Rami. It sounds like I'm on the right track then. Each project (implementation) includes multi-phase work streams, so I am listing the associated processes within the relevant process groups. As a simplified example, for one type of service, the PMs need to conduct data gathering and understand the client structure (initiating) before they can align with the client on the approach (planning) and then create the appropriate communications (executing).
...
1 reply by Rami Kaibni
Nov 11, 2016 10:43 PM
Rami Kaibni
...
You're Welcome Gail - You are indeed on the right track. However, I have the following comments on the example you've mentioned:

1- The need to gather data and understand client structure is part of planning where you define the scopecif work. Intiat9ngvshould include high level requirements, stakeholders list, bussiness goals and how they align with the companies objectives, and so on. Sort of a project charter.

2- How wil lyou close this phase ? And whats next phase ?
avatar
Gail Kaufman Retired (former project manager) CT, United States
Nov 11, 2016 1:05 PM
Replying to NOHELY COLINA
...
Yes I do, For IT Pojects We used a preliminary template disaggregated by groups of processes and then adjusted according to the particularity of the project.
Thanks, Nohely!
avatar
Gail Kaufman Retired (former project manager) CT, United States
Nov 11, 2016 1:18 PM
Replying to Anupam
...
yes sometimes, based on the requirement
Thanks, Anupam!
avatar
Gail Kaufman Retired (former project manager) CT, United States
Nov 11, 2016 1:28 PM
Replying to Mayte Mata Sivera
...
Yes, usually for IT we do.
Thanks, Maria!
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Just because english is not my first language please let me the following. Project plan is a document. I think you are talking about the project schedule. With that say, the project schedule should have the same format than the WBS (work breakdown structure). If easy to follow that guideline to maintain trazability and make easy when you change something. But it is what works for me that perhaps does not work for others.
...
1 reply by Gail Kaufman
Nov 11, 2016 9:35 PM
Gail Kaufman
...
Thanks, Sergio. I see your point. What we refer to as a detailed project management plan resembles a project schedule in that it includes linked activities with due dates. Unlike a project schedule, it does not include graphics with planned start dates and durations, but does denote who owns each activity. I guess it's a hybrid.
avatar
Gail Kaufman Retired (former project manager) CT, United States
Nov 11, 2016 8:13 PM
Replying to Sergio Luis Conte
...
Just because english is not my first language please let me the following. Project plan is a document. I think you are talking about the project schedule. With that say, the project schedule should have the same format than the WBS (work breakdown structure). If easy to follow that guideline to maintain trazability and make easy when you change something. But it is what works for me that perhaps does not work for others.
Thanks, Sergio. I see your point. What we refer to as a detailed project management plan resembles a project schedule in that it includes linked activities with due dates. Unlike a project schedule, it does not include graphics with planned start dates and durations, but does denote who owns each activity. I guess it's a hybrid.
< 1 2 >