Reporting Tolerances in a programme?

linkedin twitter facebook   Information Technology   Organizational Project Management   Using PMI Standards  
avatar
Rebecca Gordon Canberra Business Centre, Act, Australia
Does your organisation use defined reporting tolerances (eg the criteria for a traffic light rating: red, amber, green) against a programme which are different to your project reporting tolerances?
What do you see as being the main differences?
Sort By:
avatar
Igor Zdorovyak Director of Projects| Immunovant Fair Lawn, Nj, United States
Hi Rebecca,

At the beginning of a project I specify what each lighting rating is so as to minimize any confusion. Those ratings are agreed upon at the executive level as well.
avatar
Sergio Luis Conte Helping to create solutions for everyone| Worldwide based Organizations Buenos Aires, Argentina
Yes, we use it. We use traffic lights. It is because the organization considere that is the best way to visualize status at one sight.