Improving PPM Maturity: Resource Leveling

From the The Business Driven PMO Blog
by
Stories from the trenches and practical advice on how PMOs can more effectively support, prioritize and fund strategic business initiatives.

About this Blog

RSS

Recent Posts

What’s So Bad About Spreadsheets?

Top Five PPM Trends to Watch Out For in 2014

Insights and Trends: Current Project Portfolio Management Adoption Practices

Life after project completion: Is a project complete without benefits realization?

How Important is Adoption for a PMO?

Categories

2012 Takeaways, Active Projects, Adoption, Adoption Practices, Benefits Realization, Best Practices, Business Direction, Business Process, Business Value, BYOD, Clinger-Cohen, Continual Improvement, Daptiv, Daptiv Connect, Daptiv PPM, Decision Board, Decision Making, Educause 2012, Edward Deming, Events, Federal Government, Gamifiication, Gartner, Gartner Symposium, IT Governance, IT Leaders, IT Project, Lean PMO, Magic Quadrant, Mobile, Obama, optimal schedule, PMO, PMO, PMO Success Webinars, Portfolio Management, PPM, PPM Consulting, PPM solution, PPM Tools, Prioritization, Project Managers, Project Management, Project Manager, Project Managers, project managers, Project Reviews, Project Staff, Resource Leveling, Risk Analysis, ROI, SaaS PPM, Saving Projects, Scoring Models, Spreadsheets, Strategic EPMO, successful PMO, Survey, Team Collaboration, Teams, Top Management

Date

linkedin twitter facebook Request to reuse this  


A quick trip to Wikipedia yields the following definition for resource leveling: ‘a project management technique used to examine unbalance use of resources (usually people or equipment) over time, and for resolving over-allocations or conflicts.’ In other words, through resource leveling we can ensure that the project schedule is reasonable and realistic from a resource perspective – that the people or equipment needed to execute the work will be available when and where they are needed.

Sounds simple? The reality is that resource leveling needs to take multiple factors into account and can be anything but simple. And, like anything else that’s really complicated, most of us are looking for better tools to help us accomplish the task. That’s when the question about automatic resource leveling comes up.

While some project scheduling tools provide a process to see if resources are overloaded, others also provide a function that will recalculate the schedule to eliminate any overloads. As exciting as it may sound, in practice, it’s common to see that managers either never use it or even if they do, they don’t use the resulting schedule without making a lot of other adjustments. Why? Because even though automatic resource leveling can quickly ‘resolve’ overloads, it typically does it by delaying tasks until the resource is available. What it cannot do is account for human or project variables; all it does is throw some simple numbers. The solution uses elementary level math to solve a calculus-worthy problem.

While some project managers often take advantage of the speed of automatic leveling they really don’t trust the inferences drawn from the calculation to make their final decisions. They recognize that a resource leveled schedule requires a deeper understanding of the project work and the resource requirement to perform that particular task. It also requires a deeper analysis of more subtle options, tradeoffs, or variables to yield the optimal schedule.

In order to level resources in an efficient, meaningful way, a manager must keep in mind the following:

  1. Resource leveling is not just a math problem. A project manager must consider more than the singular question of effort required over the duration of a task. Instead, one must also think about what makes sense for the type of work being performed. Some tasks can be completed in less time by adding more people but sometimes splitting up the work canactually increase the time required to complete it, since multiple efforts need to be coordinated and integrated- which makes it even more time consuming. If you have a team member that needs to attend a three-day class, adding another person will not reduce the time for the class to one and one-half days.
  2. Keep an open mind. There are many different alternatives to consider when resource leveling. Sometimes it makes sense to work on multiple tasks concurrently while for other kinds of work dedicatedeffort is more practical. For example, having a team come together (either physically or virtually) to work through a plan or work through the details of a project deliverable may take less time than going through multiple cycles of email. Conversely, if we expect to have a document out for review, it is entirely reasonable to schedule the same resources that created that document to work on another task. You may also want to consider alternative ways of accomplishing the work – such as rearranging the order of tasks or using technological advances to reduce the time required for a given task. You also need to consider general workload –even though your estimates may indicate that someone can work on 20 tasks simultaneously, you may be building in inefficiency by asking people to juggle too many things at once. Ever tried reading a book in an airport and realize that you’ve just read the same paragraph three times (or more)? The fact is that each time you’re interrupted by a flight announcement, you probably don’t pick up at the exact spot you left off – you end up re-reading from a logical spot. The same happens when we try to rapidly switch between multiple tasks – the very act of switching makes us less
    efficient.
  3. Don’t try to be too precise – Remember that everything in the schedule that you’re trying to level is based on estimates – timelines may change along the course of the project. Good resource leveling requires that you keep your eye on the big picture rather than micromanaging or focusing on granularities. Also, keep in mind that the further into the future you go, the less sure you will become of everything. Give up on the notion of leveling to the hour six months into the future – resource leveling is about making a reasonable schedule, not a precise schedule. The more granular you are, the more you will need to adjust when things change.

Resource leveling is an important part of the project management process, but it can’t be done automatically. While an automatic tool may be handy, it is not a substitute for good old-fashioned common sense from a real-live human being. A software package cannot appreciate the need for variation in an individual contributor’s day, nor does it understand, as a good manager would that sometimes tasks must be performed concurrently, and they are other times when it they cannot be. The bottom-line is that an automatic tool can begin the resource leveling process, but it cannot finish it without human help.

On a closing note, if you haven’t read Fredrick Brooks’ book, The Mythical Man-Month: Essays on Software Engineering, now would be a good time.


Posted on: August 24, 2012 05:45 PM | Permalink

Comments (7)

Please login or join to subscribe to this item
avatar
Robin Goldsmith President| Go Pro Management Inc. Needham, Ma, United States
Many if not most projects these days involve both task and resource dependencies. Project management tools recognize only task dependencies and assume that resources are essentially interchangeable. In fact, many tasks can only be done by a particular resource, which creates a dependency on that resource’s availability that the tools don’t take into account when calculating critical paths and resource levels. In such instances, resource leveling not only is useless but actually can create misunderstandings.

avatar
Robin Goldsmith President| Go Pro Management Inc. Needham, Ma, United States
Many if not most projects these days involve both task and resource dependencies. Project management tools recognize only task dependencies and assume that resources are essentially interchangeable. In fact, many tasks can only be done by a particular resource, which creates a dependency on that resource’s availability that the tools don’t take into account when calculating critical paths and resource levels. In such instances, resource leveling not only is useless but actually can create misunderstandings.

avatar
Sante Delle-Vergini, PhD Senior Project Manager| Infosys Melbourne, Victoria, Australia
Interesting article, thanks.

avatar
Mansoor Mustafa Senior PM| Government Department Rawalpindi Punjab, Pakistan
thanks for sharing

avatar
Patrick Joseph Dabi Moncton, Canada
"The same happens when we try to rapidly switch between multiple tasks – the very act of switching makes us less
efficient." I am actually a firsthand victim of this scenario. Great insight! Thank you, David.

avatar
Xinsen Liao Shanghai, SH, China, Mainland
A manager must keep in mind the following:
Resource leveling is not just a math problem;
Keep an open mind;
Don’t try to be too precise;

avatar
Xinsen Liao Shanghai, SH, China, Mainland
A manager must keep in mind the following:
Resource leveling is not just a math problem;
Keep an open mind;
Don’t try to be too precise;

Please Login/Register to leave a comment.