Project Management

Notes on Reporting Progress

From the Project Confusion in Transition Management Blog
by
Projects are about transition from one state to a desirably better state. Management is often viewed as a source of confusion. So lets break down the confusion and build up the means for transition to meaningful deliveries.

About this Blog

RSS

Recent Posts

Notes on Reporting Progress (ii)

User Acceptance Tests (documentation)

Start Right

Documents Supplied for Post-HOTO

Notes on Documenting Acceptance Tests



No matter how we hard we try to keep information short and simple, there is still the minimal bits of information we should capture for keepsake. Here are some brief notes on reporting on progress - your approach likely, will be different.

The progress report would comprise minimally, the following elements:

  1. Completed tasks – Report on tasks completed within the reporting period. This include unscheduled tasks completed in a time space that may have opened-up during the reporting period. Unscheduled tasks are tasks that were planned e.g. already defined in a WBS, but not yet scheduled nor highlighted for close monitoring.
  2. In-progress – Report on tasks that are still in-progress as at the date of reporting, tasks delayed for whatever the reasons may be i.e. these have started, still in-progress but are now behind; and unscheduled tasks if any that were started because of opportunities that arise to launch these tasks.
  3. Scheduled tasks – These are planned activities for the forthcoming reporting period.

Use a table for each of the above. Information which normally accompany the above, briefly:

  1. Define the task or activity. The activity could be a work breakdown package i.e. an element of a WBS, or a sub-element, or an independent task that just has to be done. Whether work is mutually exclusive for each activity is entirely up to you.
  2. Identify the actor responsible for the task – company, role or even a nickname depending on practice.
  3. Estimate the start and completion dates. Without which we can't measure performance.
  4. Gauge the checkpoint dates to manage work estimates and progress. How checkpoint dates are used (if used) depends on a team’s need and approach to manage resources.
  5. Include any other pertinent information that may be useful for, or required by – stakeholders and reporting purposes. Examples may be a task that is delayed, subsequently suspended, and removed from a reporting period. Or whatever which may be of concern for a task or to the project at that point of reporting. 

Additional information for presentation in the report or for the progress meeting, may include:

  • Use a full-month calendar for visual clarity.
  • Use a burndown chart, for work that were defined for the reporting period.
  • List of impediments with reference to the risk register and-or issues log. Resolutions to recent-issues encountered and-or options to impediments may be included here.

 

Leaving it to you for the format of the reportClick here for an example of a project progress report.

 

 

December 2021

 

Sun

Mon

Tue

Wed

Thu

Fri

Sat

 

 

 

1

Complete stress test

2

Rectify stress test results

3

 

4

 

5

 

6

Progress report & Jan. schedule

7

 

8

 

9

 

10

 

11

 

12

 

13

Construct modules for Phase 2

14

 

15

 

16

 

17

 

18

 

19

 

20

 

21

Test modules

22

 

23

Complete module tests

24

Rectify results

Plan for integration 

25

 

26

 

27

 

28

 

29

Integrate modules

30

 

31

 

 

Posted on: April 18, 2022 04:46 AM | Permalink

Comments (1)

Please login or join to subscribe to this item
Thank you, good overal general background on project status reports. In my experience, Financial reporting is absolutely key, so it should be mentioned here in status reporting. It's a little difficult to understand the first sentence, suggest to rephrase and edit: "No matter how we hard we try to keep information short and simple, there is still the minimal bits of information we should capture for keepsake."
Thank you

Please Login/Register to leave a comment.

ADVERTISEMENTS

"Anyone who has never made a mistake has never tried anything new."

- Albert Einstein

ADVERTISEMENT

Sponsors