Project Management

HOW is as important as WHAT when requesting work progress updates

From the Easy in theory, difficult in practice Blog
by
My musings on project management, project portfolio management and change management. I'm a firm believer that a pragmatic approach to organizational change that addresses process & technology, but primarily, people will maximize chances for success. This blog contains articles which I've previously written and published as well as new content.

About this Blog

RSS

Recent Posts

Leading Through Crisis Means Leading Through Context

"It's the end. But the moment has been prepared for." - retirement lessons from the Doctor

Just because they are non-critical, doesn't mean they are not risky!

Just because they are non-critical, doesn't mean they are not risky!

How will YOU avoid these AI-related cognitive biases?

Categories

Agile, Artificial Intelligence, Career Development, Change Management, Communications Management, Decision Making, Governance, Hiring, Kanban, Lessons Learned, Personal Development, PMO, Portfolio Management, Project Management, Resource Management, Risk Management, Risk Management, Schedule Management, Scheduling, Tools

Date

linkedin twitter facebook Request to reuse this  

Categories: Project Management


Whether we are looking at project or operations, understanding what progress has been made with the individual work items owned by your team is part of a normal day or week's work for most leaders. This information is critical to using tools such as earned value management and information radiators such as burn down or burn up charts.

But how you ask for work item updates will influence the quality of the work performance data you receive.

If the work items are small enough and are likely to be completed within a single reporting period, an effective, objective method is to report status as not started, not done or done. The expectation is that work items which are reported as being in a not done state will move to done by the next status review or would be escalated as being blocked.

However, when work items are not small, greater granularity of reporting for work items in progress might be warranted.

Here are three of the more common ways I've seen this information requested:

  • What percentage of work has been completed?
  • How much time (effort or duration) have you spent on the work item?
  • How much time (effort or duration) is remaining to complete the work item?

Except in situations where progress can be independently and quantifiably assessed, the first method suffers from the Ninety-Ninety Rule of Project Schedules: The first ninety percent of the task takes ninety percent of the time, and the last ten percent takes the other ninety percent!

And even if you are able to objectively measure percentage complete, it still assumes that past performance on the work item will persist till the work item is completed. The second method is even worse as it only considers the past and doesn't educate us on what the future might hold.

The third approach has the benefits of forcing the team member to check if the expected remaining effort or duration for the work item is accurate and if it is not, a re-forecast can be done.

Putting theory aside, I wanted to see what was actually happening in practice.

I ran two similar polls for a week in PMI's LinkedIn Project, Program and Portfolio Management group and on ProjectManagement.com. I received 239 responses with the following breakdown of votes:

  • How much work is left: 49%
  • What percentage is done: 29%
  • Is it done or not: 16%
  • How much work have you done: 6%

It is encouraging to see that the two better methods are used in almost two-thirds of cases. However, this means that a third of respondents are using the methods which are least helpful in forecasting what may happen in the future.

Requesting useful progress updates is yet another case of "It's not what you say, it's how you say it"!

 


Posted on: May 01, 2022 07:00 AM | Permalink

Comments (9)

Please login or join to subscribe to this item
avatar
Michael Hilbert Director of Project Management| TuWay Communications Bethlehem, Pa, United States
Kiron,

Your final comment on what is said vs how it is said is spot on. This also applies to the answer you receive. Sometimes you can ask the right question, but get an ambiguous answer, which is somewhere between fantasy and reality. Knowing when to dig further and ask follow up questions, it a key part. Trust...But Verify when needed.... Thanks for the insightful post.
Mike

avatar
Luis Branco CEO| Business Insight, Consultores de Gestão, Ldª Carcavelos, Lisboa, Portugal
Dear Kiron
The topic that you brought to our reflection and debate was very interesting.

Thank you for sharing, for your opinions and for the results of your research.

Was it worth asking the question here in our community, ProjectManagement.com?

It completely missed me :-)

avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Thanks Mike!

Thanks Luis - yes, I did get a lot more responses by polling both communities, but didn't really find a way to promote the poll here without falling afoul of the community guidelines. Perhaps you know a way to do this so I can use that method for my next poll which is currently running?

Kiron

avatar
Luis Branco CEO| Business Insight, Consultores de Gestão, Ldª Carcavelos, Lisboa, Portugal
Dear Kiron

I am convinced that what you publish is in the interest of the community

When you chose to collect and share members' opinions on topics, you certainly had a greater purpose.

If community rules prevent you from sharing the opinions of project management professionals with us (the more opinions the better), there's nothing like changing the rules :-)

I think it's a topic you can talk to the managers of this community about.

Footnote: Don't turn to ambassadors because those are long gone in cyberspace :-)

avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Thanks Luis - I'll reach out to Heather to see what's acceptable as far as poll promotion goes!

avatar
Warren Simon Program Manager| DoD Baltimore, Md, United States
Interesting article. Thanks for your thoughts.

avatar
Kiron Bondale Retired | Mentor| Retired Welland, Ontario, Canada
Thanks Warren!

avatar
Stéphane Parent Self Employed / Semi-retired| Leader Maker Prince Edward Island, Canada
The tricky part with asking how much time there is left on an activity is the work involved to reflect the information in your schedule. It's definitely more laborious than updating the percentage of work done!

avatar
Binay Samanta Director| Project & Environment Consultants Dhanbad, Jharkhand, India
Work progress can be found any time by proper project scheduling and monitoring

Please Login/Register to leave a comment.

ADVERTISEMENTS

Love can sweep you off your feet and carry you along in a way you've never known before. But the ride always ends, and you end up feeling lonely and bitter. Wait. It's not love I'm describing. I'm thinking of a monorail.

- Jack Handey

ADVERTISEMENT

Sponsors